Learn who to contact regarding the projects listed on this page.
Project | Contact Information |
---|---|
Fullerton Reservoir | Construction Contracts Administration Division Phone: 410-887-3531 |
Windsor Mill Road Improvement Project | Email: windsormillproject@baltimorecountymd.gov |
Old Frederick Road on Frederick Road Slope Stabilization | Multiple options were presented at a community meeting, including:
The community has until Friday, September 9 to provide feedback by emailing hkadivar@baltimorecountymd.gov. |
All Other Projects | Email engineering@baltimorecountymd.gov and include the name of the project as it appears in the below table as the subject line of your email. |
Fullerton Reservoir
Learn more about the $78 million-dollar reservoir project's design and development over 50 years and its capacity to ensure an adequate water supply for the region. View a rendering of the finished project, in which three reservoirs will be built.
Construction will begin in January or February. Normal construction hours will be 7 a.m. to 5 p.m. and involve 8 to 15 workers. Our contract will include noise restrictions borrowed from old State of Maryland regulations: 65 decibels at the property line from 7 a.m. to 10 p.m. and 55 decibels at the property line from 10 p.m. to 7 a.m.
Three reservoirs must be built, because with one reservoir out of service, pipeline and valve restrictions make it impossible to pass all of the treatment plant flow through a single remaining reservoir. Two reservoirs must be in service at all times to handle the treatment plant flow and a third reservoir is required for necessary operational flexibility. The reservoirs could be buried, but there is no reason to do so once it is understood that they cannot be lowered into the ground because their overflow elevations (the elevation above sea level) have to be compatible with the overflow elevations of Druid Lake and Curtis Bay Tank.
The project will require removing trees, however, we will attempt to preserve as many trees as possible. Additionally, we will be planting some smaller trees as part of our landscaping plan, which is still under development.
Major concrete pours will continue through the night until the respective pour is complete, when there likely will be about 45 workers onsite. There will be about six pours, during there will be a steady flow of concrete trucks to and from the site until the pour is complete. Trucks will line up along the access road inside of the property; if this becomes a problem during construction, we will have some of the trucks line up along the Fullerton Pumping Station driveway. It will be a contract requirement for all major concrete pours that the concrete trucks must enter and leave the site by way of Perry Hall Boulevard and the eastern portion of Bucks Schoolhouse Road.
After the reservoirs are constructed and in service, we anticipate the site will be visited by one or two Baltimore City maintenance crews daily. Additionally, there will be approximately one chemical delivery (sodium hypochlorite for disinfection) a month.
The details of security lighting are still under design, but minimal lighting around the reservoirs, the disinfection building and at the entrance, can be expected. The reservoir facilities will be secured by fencing and the remainder of the property will be reserved for use by the future Fullerton Filtration Plant project, which also must be secured once constructed. We are exploring all options to ensure safety and plan to consult our traffic engineering staff to determine the utility of a one-way road.
The project has been delayed twice for multi-year intervals each time. The first delay occurred when the project was put on hold so that the Fullerton Filtration Plant study could be performed. Baltimore City and Baltimore County agreed there was a possibility the reservoirs could negatively impact the future filtration plant and the prudent course of action was to study the filtration plant before proceeding any further with design of the reservoirs. After the filtration plant study was completed, there was a second delay due to cost-share negotiations.
Windsor Mill Road Improvement Project
This project will support pedestrian safety and vehicular capacity improvements along Windsor Mill Road from Featherbed Lane to Woodlawn Drive by widening the roadway from an existing pavement width of 22 feet to a proposed width of 36 feet (from Featherbed Lane to Woodlawn Drive, approximately 3,400 feet) and by including five-foot sidewalks on both sides of the road. This roadway segment is an essential connection for transit commuters and provides accessibility for adolescents to and from school. This project will have many benefits, including:
- Providing a safe and accessible route for the drivers and pedestrians along this roadway
- Satisfying the various requests of the Gwynn Oak community by satisfying their various requests
- Enhancing the County's accountability in identifying existing infrastructure for rehabilitation and safety improvements
The pavement widening will include:
- Additional storm drain systems
- New curb and gutter
- Water main installation
- Relocation of existing major utility poles
Land acquisition will be required by numerous adjoining property owners. This segment is flanked with residential homes and heavily traveled by vehicles and pedestrians due to the Maryland Transit Administration (MTA) bus stop located at the intersection of Windsor Mill Road and Woodlawn Drive.
- View the Phase Map
- View Phase One Map
- Watch the video of the June 22, 2021 meeting.
By District
The following are lists of current engineering projects by council district. This information is updated on a monthly basis. We also provide an interactive map to view the location of projects.
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
Water Main Replacement on Johnnycake Road | Replacing 11,500 feet of eight-inch water main on Johnnycake Road south of I-70. Crews are completing tie-ins. The project was scheduled to take two years. | October 2021 Two years | $3,152,179 | 98 |
Sewer Rehabilitation in Catonsville | Rehabilitating more than 60,000 feet of sanitary sewer line in Catonsville. Crews from the County's contractor (SAK Construction) will be working in the neighborhood east of North Rolling Road and south of the Baltimore National Pike (Route 40) in Catonsville. Residents can expect minimal, short-term disturbance as work proceeds and may be asked to move parked vehicles or reduce their wastewater discharge for a few hours while sewer pipes are being relined. The main lines have been completed and crews continue to vacuum test manholes. The project should be completed by the end of the month or early April. | August 2021 < One year | $4 million | 98 |
Water Main Replacement on Maiden Choice Lane and Kenwood Avenue | Replacing 7,000 feet of failing, cast-iron water mains with new 12-inch and eight-inch diameter lines, at two locations: Maiden Choice Lane (between Kenwood Avenue and Wilkens Avenue) and Kenwood Avenue (between Maiden Choice and Wilkens Avenue). |
| $2.3 million | 99 |
Lower Powder Mill Interceptor Rehabilitation | Rehabilitation of the Lower Powder Mill Sewer Interceptor. The line is 5,535 feet long. Much of the relining has been completed. Crews are working on the punch list and the final video inspection. | April 2021 > One year | $4,625,368 | 99 |
Washington Boulevard Water Main | Replacing an old 16-inch diameter water main on Washington Boulevard (between Clark Boulevard and the CSX railroad tracks) which has been prone to breaking, with 1,200 feet of new pipe. The old pipe dates from 1950. |
| $400,000 | 95 |
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
Powder Mill Interceptor Relief Sewer | One mile of new sanitary sewer in Lochearn in February. The project extends from Liberty Road (at the City line) to Southern Cross Drive at Parsons Avenue. Tree removal to permit excavation for 5,621 feet of large-diameter conduit. The new line increases pipe capacity and will help prevent sewer overflows. This is part of the Baltimore County agreement with the EPA to eliminate overflows and to improve an aging sanitary sewer system. | Expected completion in spring 2024 | $5.7 million | 1 |
Reisterstown Road Water Main Project Phase III | Replacing 16,000 feet of line in Reisterstown Road between Pleasant Hill Road and Stocksdale Avenue. Three miles of new, 16- and 20-inch diameter line. Crews are currently putting services across Reisterstown Road. | Expected completion in spring 2024 |
| 58 |
Water Line Construction on Falls Road | Replacing more than 11,000 feet of water line on Falls Road between the Baltimore City line and Brightfield Road near I-695. The replacement of the 90-year-old line sections will improve the reliability of the system. Much of the construction will be done between 9 p.m. and 5 a.m. and ingress and egress will be coordinated with property owners. Falls Road will not be closed during construction, but there will be some lane closures during the day to accommodate construction schedules. Falls Road carries about 18,000 cars daily. There will be traffic delays. | N/A Two years | $10.5 million | 28 |
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
Rural Roads Meeting | The Department of Public Works and Transportation will hold its annual public meeting to discuss rural roads, bridges, repaving and traffic issues at Oregon Ridge Park, 13401 Beaver Dam Road, Cockeysville, Maryland 21030 on Tuesday, April 25 from 5:30 to 7:30 p.m. The meeting fulfills the County's pledge to meet annually with residents interested in preserving the rural character of Baltimore County and to apprise them of infrastructure plans. For more information, call the Director's Office, Department of Public Works and Transportation at 410-887-2171. | |||
Sewer Relining Project in Carney, Perry Hall and Towson | Extensive sewer relining project in Carney, Perry Hall and Towson. More than 12 miles of sanitary sewer pipe will be relined. Most of the work will be below ground with minimal impacts to communities. However, with any project of this scale, there may be some traffic or parking issues and occasional chemical odors. | May < One year | $5.8 million | 98 |
Sewer Pumping Station in Cockeysville | Modernizing the Cockeysville Pumping Station. | Complete | $5,215,000 | 100 |
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
Rural Roads Meeting | The Department of Public Works and Transportation will hold its annual public meeting to discuss rural roads, bridges, repaving and traffic issues at Oregon Ridge Park, 13401 Beaver Dam Road, Cockeysville, Maryland 21030 on Tuesday, April 25 from 5:30 to 7:30 p.m. The meeting fulfills the County's pledge to meet annually with residents interested in preserving the rural character of Baltimore County and to apprise them of infrastructure plans. For more information, call the Director's Office, Department of Public Works and Transportation at 410-887-2171. | |||
Reisterstown Road Water Main Project (Designated Phase III) | Major water main project, replacing 16,000 feet of line in Reisterstown Road between Pleasant Hill Road and Stocksdale Avenue. Three miles of new, 16- and 20-inch diameter line. | N/A Spring of 2024 |
| 58 |
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
Sewer Project Perry Hall Manor | Connecting 104 homes in the Perry Hall Manor area in a long-term project to provide sewer service. In September, residents saw topographical and environmental surveyors gathering information for the design phase, which should begin later this year. The surveyor work has been completed; more field work is anticipated. | Two years 1.5 years | 100 | |
Sewer Relining Project in Carney, Perry Hall and Towson | Extensive sewer relining project in Carney, Perry Hall and Towson. More than 12 miles of sanitary sewer pipe will be relined. Most of the work will be below ground with minimal impacts to communities. However, with any project of this scale, there may be some traffic or parking issues and occasional chemical odors. | May 2022 1.5 years | 5.8 million | 98 |
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
Herring Run Basin 17 and 33 | This construction is the next phase of the Herring Run Project. | April 2022 2024 | $6.5 million | 30 |
Orems Road Basin 3 Relief Sewer | 900-foot long relief sewer in the Orems Road area of Middle River, which includes a tunnel at the intersection of Eastern Boulevard and Kingston Road. Work is being rescheduled to accommodate drilling modifications. | $1.1 million | 1 | |
Stansbury Manor Pumping Station | The Stansbury Manor Sewage Pumping Station (a new station) is under construction. Work began in January 2022 and should be completed in January 2024. The project is expected to cost $5,045,000. | January 2022 January 2024 | $5,045,000 | 52 |
Red House Run Structural Sewer Rehabilitation | Major sewer rehabilitation project consisting of 15 miles of sewer line in the Overlea and Rosedale areas. It should be finished by the end of 2023. The Red House Run Structural Sewer rehabilitation project is part of the County's Consent Decree, its agreement with the EPA to improve the entire sanitary system and eliminate sanitary sewer overflows. | June End of 2023 | $4.7 million | 25 |
Parkville: East Branch Herring Run Relief Sewer | The project involves two tunnels and consists of more than 11,000 feet of new pipe and 28 manholes. Crews will work on Taylor Avenue, Wendover Avenue, Birmingham Avenue, Aiken Avenue, Oakleigh Road, Darlington Drive and Queen Anne Drive. | February 2020 Two years | $16,177.00 | 88 |
Sewer Relining Project in Carney, Perry Hall and Towson | Extensive sewer relining project in Carney, Perry Hall and Towson. More than 12 miles of sanitary sewer pipe will be relined. Most of the work will be below ground with minimal impacts to communities. However, with any project of this scale, there may be some traffic or parking issues and occasional chemical odors. | May 2022 1.5 years | $5.8 million | 98 |
Essex Structural Sewer Rehabilitation | Structurally rehabilitating sewer lines in Essex in the area of Eastern Boulevard, Mace Avenue and Riverside Drive. The County's contractor will line almost 15 miles of sewer pipe (eight, 12, 15 and 18-inch diameter conduits) during the next year. | < One year | $4.4 million | 93 |
Hyde Park Pumping Station | Improving the Hyde Park Sewage Pumping Station located near Back River and Muddy Gut. The project is in final completion. | January 2020 2022 | $2,669,230 | 97 |
Brien Run Sewer Rehabilitation | Rehabilitating sewer lines in the Brien Run area south of Pulaski Highway. The main lines have been completed and they are being inspected by video. Inspectors are working on the punch list. | March 2020 2023 | $7 million | 99 |
Bauernschmidt Manor Pumping Station | Upgrades to the Bauernschmidt Manor Sewage Pumping Station were expected to be finished during the summer of 2020, but delayed due to supply problems caused by COVID-19. | July 2019 | $2,137,554 | Final completion |
Harewood Park Sewer Pumping Station | Renovating the Harewood Park Sewer Pumping Station at 12901 Princeton Road in Chase. | July 2018 | $3.3 million | Final completion |
Mohrs Lane Bridge | The Mohrs Lane Bridge (Bridge B-0143) over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in 2011 at no cost to Baltimore County, which assumed ownership with plans to rebuild the span. A new bridge is currently awaiting the completion of the engineer's design. The structure is scheduled to be advertised for construction January 2024. This bridge will be part of the future Campbell Boulevard Corridor. | Design completed in early 2023 |
|
|
Project | Description/Updates | Start Date/Duration | Cost | Percent Complete |
---|---|---|---|---|
North Point Sewer Force Main | Replacement of 6,600 feet of sewer force main in North Point from Penwood Terrace to Willow Avenue. During the project, there will be single-lane road closures to permit construction. | April 2023 April 2024 | $3.1 million | |
Red House Run Structural Sewer Rehabilitation | Major sewer rehabilitation project consisting of 15 miles of sewer line in the Overlea and Rosedale areas. The Red House Run Structural Sewer rehabilitation project is part of the County's Consent Decree: it's agreement with the EPA to improve the entire sanitary system. | June 2022 End of 2023 | $4.7 million | 25 |
Millers Island Sewage Pumping Station | Renovation of the Millers Island Sewage Pumping Station at 8819 Millers Island Road 21219. A sewer bypass was installed on October 22, 2021 in preparation for the project, which includes electrical and mechanical work in addition to a new roof and generator. | 2021 This year | $3 million | 94 |
Turkey Point Pumping Station Rehabilitation | Renovating Turkey Point Sewage Pumping Station. | This year | $3.2 million | 96 |
Bread and Cheese Sewer Improvements | Relining 26,000 feet of eight-inch diameter sewer pipe in the Bread and Cheese Creek area. The project is waiting for the completion of video inspection of the line. |
| $2.25 million | 99 |
Saint Helena Water Main Project | Replacing 13,600 feet of failing cast iron water pipe this fall on Saint Helena Avenue (from the City Line to Dundalk Avenue) and in the area between Oak Avenue and Maple Avenue. Crews began working following mobilization. | February 2021 End of 2023 | $5.5 million | 75 |
Gray Manor Sewer Shed Structural Rehabilitation | Contractors began an extensive rehabilitation of the Gray Manor Sewer Shed in mid-December 2020. Crews will reline 37,369 feet of eight-inch and 36-inch sewer pipe. | More than one year | 99 |