March 15, 2019 – Council District 6

  1. EPS Variances
  2. Planning Board Meetings
  3. Harewood Park Sewer Pumping Station
  4. Water Improvements in Victory Villa
  5. Campbell Boulevard
  6. Sewers: Herring Run Structural Rehabilitation Phase 1
  7. The Future Fullerton Reservoirs
  8. Mohrs Lane Bridge
  9. Administrative Variances
  10. Development Meetings
  11. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 6

Planning Board Meetings

Baltimore County Planning Board meetings are scheduled as follows:

  • Thursday, March 21, at 4 p.m., in Room 104, Jefferson Building, 105 West Chesapeake Avenue in Towson

Information: Contact Ngone Seye Diop by phone at 410-887-3482 or by email at nseyediop@baltimorecountymd.gov.

Harewood Park Sewer Pumping Station

Baltimore County has begun renovating the Harewood Park Sewer Pumping Station at 12901 Princeton Road in Chase. Work on the $3.3 million project officially began in July—it's now 23 percent complete—and will take about a year to finish.

Information: Email engineering@baltimorecountymd.gov.

Water Improvements in Victory Villa

Baltimore County is investing $2.5 million dollars in the Victory Villa area to replace aging cast-iron water pipes in order to improve water quality, reliability and fire protection. The work, which began in January and should take a year to finish, will replace 9,700 feet of six-inch and eight-inch diameter cast-iron line. The project is 20 percent complete.

Information: Email engineering@baltimorecountymd.gov.

Campbell Boulevard

Baltimore County is extending Campbell Boulevard from Bird River Road to Windlass Run. Construction of the $5 million project began in October and is expected to take about a year and a half to complete.

Information: Email engineering@baltimorecountymd.gov.

Sewers: Herring Run Structural Rehabilitation Phase 1

Baltimore County is rehabilitating 81,000 feet of sewer line spread throughout Council Districts 5 and 6. Work has progressed about 99 percent toward completion. It is expected to cost $4,640,123.

Information: Email engineering@baltimorecountymd.gov.

The Future Fullerton Reservoirs

In February 2017, the Department of Public Works and Transportation and Transportation broke ground on the Fullerton Reservoirs—three have been planned for the site. Construction is expected to take about three years and cost $80.1 million. Engineers estimate that the project is now about 83 percent complete. The construction site is bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard.

Information: Call the Bureau of Engineering, Water Design at 410-887-3783 or email engineering@baltimorecountymd.gov.

Mohrs Lane Bridge

The Mohrs Lane Bridge (Bridge B-0143) over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in 2011 at no cost to Baltimore County, which assumed ownership and plans to rebuild the span. A new bridge is currently being designed with construction scheduled to begin by late 2020. This bridge will be part of the future Campbell Boulevard Corridor.

Information: Email engineering@baltimorecountymd.gov.

Administrative Variances

Administrative Variances pending include requests for Administrative Variances pending before the Department of Permits, Approvals and Inspections. These hearings up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or call Zoning Review at 410-887-3391.

There are no Administrative Variances pending at the time of publication of this newsletter. Please visit the Zoning calendar for changes in District 6.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

There are no Development Meetings scheduled at the time of publication of this newsletter. Please visit the Development Management Calendar for changes in District 6.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or call Zoning Review at 410-887-3391.

Zoning Hearings—105 Dihedral Drive
Date and Time: Thursday, March 28, 11 a.m. to noon
Case Number: 2019-0190-A
Property Location: South side of Dihedral Drive, east of Fuselage Avenue
Legal Owners: Veronica Gardner, Anthony Bugan
Variance to permit a proposed addition with a rear yard setback of 23 feet in lieu of the required 30 feet and to permit an existing and proposed side setback of seven feet in lieu of the required 10 feet.
Hearing Location: Jefferson Building, 105 West Chesapeake Avenue, Room 205, Towson, Maryland 21204