Skip Navigation

Francis Scott Key Bridge Incident Updates
Watch the Recording of County Executive John A. Olszewski Jr. delivering the Proposed FY25 Budget Message

Perry Hall Manor Sewer Extension Project

The Department of Public Works and Transportation (DPWT) is planning to install a public sewer system in the Perry Hall Manor community. The sewer system will consist of:

  • Two-inch, low-pressure sewer mains
  • Eight-inch gravity sewers
  • Individual grinder pumps
  • Four-inch pressure main
  • A new pump station

Improvements to the road surface will also be made anywhere the system is installed underground.

The County is planning to extend public sewer to the Perry Hall Manor community for health reasons. Currently, the wastewater generated by the homes within the community is treated and disposed of by individual, onsite septic systems, some of which are failing. A study that concluded in April 2020 explored all options for collecting this wastewater and ultimately conveying it to the County's public sewer system. The study found that installing approximately 9,000 feet of gravity sewer, grinder pumps, 2,000 feet of low pressure main, a sewage pumping station and 1,400 feet of force main discharging to the adjacent neighborhood's public sewer was the best option to replace these structurally deficient, aging and failing septic systems.

Project Timeline

Currently the project is in the final engineering design phase. DPWT anticipates completing the design, right-of-way acquisition, environmental clearances and advertising the project for construction in early 2025. Construction is expected to start in the summer of 2025 and is expected to be completed in late 2027. All dates are contingent on clearing rights-of-way, property acquisition for the pump station and obtaining the necessary environmental permits in a timely fashion.

Impacts

Impact permits and mitigation plans will be submitted to the applicable resource agencies prior to the commencement of construction activities. During the construction phase, residents will experience:

  • Road closures during the work day
  • Construction traffic and equipment moving in the area
  • A pump station will be built—Fencing and landscaping will be installed to make this station as inconspicuous as possible.
  • County contractors will install grinder pumps for individual homes that require them, in turn the County will need access to each property—These locations will be determined and surveyed and most likely be close to the currently installed septic systems. The County will continue to own and maintain the grinder pumps for residents that require them.
  • Any impacts to protected resources are anticipated to be minimal.

Background

The 2018 septic system assessment (Sanitary Survey) conducted by the Department of Environmental Protection and Sustainability (EPS) found nearly 20 percent of the homes in Perry Hall Manor to be in immediate need of a septic system repair. View a map of the surveyed area. The recommendation by EPS to extend the sewer was based on a variety of factors, including the:
  • Age of existing septic systems
  • Close proximity to private drinking water supplies
  • Known septic system problems
  • Lack of area to repair septic systems
  • High cost and anticipated complication with future septic system repairs and replacements
  • Soil conditions

In September 2021, separate public meetings were offered to each of the following groups affected by the project, though residents were able to attend either or both:

  • Residents with nonfailing or marginal septic systems who were offered the option to connect to public sewer. Watch the meeting recording.
  • Residents who have failing or marginal systems who are required to connect to public sewer. Watch the meeting recording.
  • View the full presentation. The presentations at these meetings were almost identical, however, the version presented to the optional connection audience discussed the disadvantages of not connecting during the project (page 26 of the presentation).

A second community meeting was held on June 1, 2022, at the American Legion Post 130. View the full presentation. View the question and answer document.

About the Sanitary Survey

Read more about the process below:

  1. Data Review—EPS reviewed all available data in their files regarding existing well and septic info, perc tests, soil maps and water quality.

  2. Door-to-Door Visits to Properties—EPS went door-to door, attempted to meet with every property owner to locate each well and septic system using GPS units. Notes were left at each door of those that were not home, requesting that they contact the Metropolitan District Financing and Petitions Office to discuss any issues or concerns about their wells or septic systems.

  3. Physical Inspections—EPS conducted basic, physical inspections of each septic system that was accessible. Inspections focused primarily on sewage levels and hydraulic capacity.

    1. Failing or marginal systems are unlikely to pass a thorough inspection for a property transfer. These systems were identified as:

      1. Systems observed to be hydraulically loaded (at capacity)
      2. Systems that reported problems with frequent back-ups
      3. Systems where there was sewage effluent on the surface
    2. Water wasn’t identified as having any significant issues and EPS was not aware of water yield or quality issues beyond approximately five properties. Public water was not added as part of this project. The extension of public sewer eliminates the discharge into the ground and causes less constraint on each property because water supplies would not be restricted by the limitations of a septic system.

Engineering and Design

The location of house connections, ancillary structures, and the sewer main tie-in point to the existing sanitary sewer system will be established when developing the hydraulic design of the sewer mains. Our preliminary approach is to provide for the proposed sewer mains to be installed along existing rights-of-ways (roads) allowing service for all properties along its path. 

If a property owner indicates on their response form that they want to connect to the system, the County will factor that property into the design of the system. Please note that if the lowest bid received is 20 percent or more than the estimated costs, the contract will be rebid. The County is committed to keeping the community informed of the progress throughout this process.

Connection

In accordance with County Code and departmental policy, you must connect your property to the public sewer system and abandon the septic system. Connection to the sewer system must be within one year of the Notice of Completion and release of the system, the only exception being if you have received a violation notice from EPS that your sewage disposal system is failing, in which case, connection must be made within 30 days.

The licensed plumber hired by the property owner to make the sewer connection will be responsible for pumping the septic system (and drywells if present) and backfilling with clean fill or stone as part of the permit requirements.

For Those Who Choose Not to Connect

If your septic system fails and a public sewer is available to the property, a connection to public sewer will be required. EPS will not issue a permit to repair a failed septic system if public sewer is determined to be available. Property owners who choose not to connect will not be able to finance their connection charges through the County if they decide to connect later. When a property owner’s septic system fails, they will be responsible for hiring a utility contractor and paying the full amount. Improvement permits may not be allowed without a connection to the system. If you want to add a pool or an addition, you will be required to connect to the system.

Costs and Charges

Plumbing Permit Charges

The cost of plumbing permit consists of several charges:

  • System connection charge: $875—Included in the construction loan charges
  • Sewer house connection: $30
  • Connection for all existing sewer fixtures: $30
  • Sewer service prorated charge—This is a variable fee that depends on the month the permit is applied for and how many plumbing fixtures are in the home.
  • Plumber’s bill—Owners of residential properties may finance their plumber’s bill for 40 years at the same interest rate as the true interest cost in the County’s most recent issuance of Metropolitan District Bonds at the Final Notice of Special Assessment up to five percent. Financing your plumber’s bill will result in an increase in the construction loan charge on the tax bill. 

Assessment and Annual Rates

Each property’s charges are determined by their average front foot assessment. This means that each property owner will pay towards the sewer benefit and deficit charges, depending on their assessment. Plumber’s bills may vary as well.

Sewer Benefit Assessment is a special assessment levied to recover construction costs for sewer mains. Normally amortized over 40 years at 6.42 percent interest, this charge may be paid off in full at any time. All properties are assessed, improved and unimproved. Assessable footage is normally the average width of a property, however, some properties may also be assessed for a side or parallel street frontage abutting a sewer main. The annual charge for residential property having assessable footage greater than 200 feet is computed using a “small acreage breakdown” providing that there is only one structure on the property to be connected to the sewer. Below are the per-foot rates used to compute the benefit assessments and annual benefit charges.

View a sample notice of assessment.

Property TypeAssessment RatesAnnual Rates
Residential$28.57$2
Business$44.29$3.10
Small Acreage First 200 Feet: $2
Second 200 Feet: $1.35
Over 400 Feet: $0.65

About Your Property Tax Bill

If homeowners plan to sell before or during the project, costs and decisions transfer with the home through the tax bill, from the County to the property owner.

The annual sewer benefit and construction loan charges will be added to the property tax bill you receive in July following the Notice of Completion.

Benefit assessments and construction loan charges are liens on the property, however, the County treats them as assumable liens. The County does not require that these charges be paid off to sell or transfer the property to a new owner, except in certain situations involving property subdivisions and commercial properties.

All property owners, regardless of whether they choose to connect, must pay the charges in Lines 1 and 2a. These charges help cover the cost of extending the option of public sewer service to the property—a benefit that provides a critical public service to the community and that can increase the value of your property.

Payment and Financing

The funding options are the same for those who are required to connect and those that opted to connect. For the Bay Restoration Fund, highest priority is given to those with failing septic systems, however any qualifying property owner can apply. There are several options for paying for the sewer connection.

Learn more about Countywide tax credits and tax relief programs.

Explore Metropolitan District Financing

 

Contact Us

Perry Hall Manor Sewer Extension Project

111 West Chesapeake Avenue
Room 219
Towson, Maryland 21204

Hours

Monday through Friday
8 a.m. to 4:30 p.m.

Phone

BALTCOGO311

Staff Contact

Chris Korpman

 

Follow for Updates