December 15, 2020 – Council District 5

  1. EPS Variances
  2. Planning Board Meetings
  3. Water Line Replacement in Towson
  4. Towson Improvements
  5. Stoneleigh-Anneslie Storm Water Project
  6. Water Improvements on Forge Road
  7. The Future Fullerton Reservoirs
  8. Administrative Variances
  9. Development Meetings
  10. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 5

Planning Board Meetings

The board will meet virtually as follows:

  • No meetings scheduled for December.

Please check the Planning Board Meetings page for a link to the meeting, information on participating in the virtual meeting, the meeting agenda and any last-minute schedule changes.

Information: Contact Chris Davis by phone at 410-887-3482 or by email at cdavis1@baltimorecountymd.gov.

Water Line Replacement in Towson

Baltimore County is replacing 1,800 feet of old cast-iron water main in Fairmount Avenue between York and Bosley Roads in Towson with a new 24-inch diameter line. The work includes the installation of a new valve and has officially started with stake outs; it’s eight percent toward completion. The project, which will cost $2.4 million, should be completed by the early spring.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Towson Improvements

In cooperation with the Towson Row development, the Department of Public Works and Transportation and Transportation and Transportation is improving sidewalks on Chesapeake Avenue between Washington Avenue and York Road. The majority of construction on the north and south sides is now complete. The remaining work includes the access to the future Whole Foods store on the south side of Chesapeake Avenue, which will be completed in the summer.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Stoneleigh-Anneslie Storm Water Project

The Department of Public Works and Transportation and Transportation and Transportation is addressing storm water concerns in the Stoneleigh-Anneslie community and updating the century-old drainage system. Baltimore County earmarked $1 million for the project in 2018. A system was designed last year and the County's contractor began work in February with the relocation of water lines. Work is ongoing (following COVID-19 delays in the spring) and crews are installing pipes and manholes on Kingston Road, Wardman Avenue, Marlborough Road, Avondale Road and a part of Regester Avenue. Completion is expected by the summer. Working hours, traffic changes, temporary water shut-offs and parking impacts are being announced as the job progresses.

Information: Email the Bureau of Engineering and Construction, Storm Water Division, at engineering@baltimorecountymd.gov.

Water Improvements on Forge Road

Baltimore County is replacing 2.64 miles of water line on Forge Road between Belair Road and Gaylord Street. The $3 million project, replacing old 12-inch diameter cast-iron pipes, began in November 2019 and is scheduled to be completed this fall. It is 95 percent complete. Paving may be done before the end of the year or in early spring.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

The Future Fullerton Reservoirs

The three-year-long construction of the Fullerton Reservoirs, costing $80.1 million, is 99 percent complete. Crews are currently building an ancillary building to facilitate water chlorination and landscaping will be completed in the spring.

Information: Call the Bureau of Engineering and Construction, Water Design at 410-887-3783 or email engineering@baltimorecountymd.gov.

Administrative Variances

Administrative Variances Pending include requests for Administrative Variances pending before the Department of Permits, Approvals, and Inspections. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or Zoning Review at 410-887-3391.

There are no Administrative Variances pending at the time of publication of this newsletter. Please visit the Zoning calendar for changes in District 5.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

Development Review Committee—The Shops At Perry Hall
Date and Time: Tuesday, December 15, 2 to 3 p.m.
Property Location: 9705 Honeygo Boulevard
Meeting Location: Webex—County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
DRC Number: 121520C
PAI Number: 11-1086
Tracking Number: DRC-2020-00167
Request: The request is pursuant to Baltimore County Code, Section 32-4-106(b)(2) for the 1st Refinement to the approved development plan for the Shops at Perry Hall.
Information: Contact Lloyd T. Moxley at lmoxley@baltimorecountymd.gov or 410-887-3321.

Consolidated Zoning and Development Plan Hearing—Red Maple Place
Date and Time: Wednesday, December 16, 10 a.m. to Noon
Property Location: 407 East Joppa Road
Legal Owners: Red Maple Place
Zoning Case Number: 2020-0267-A
Variance, if necessary, to allow a maximum building height of 45.5 feet, with a 10-foot extension for the stair tower for maintenance access to the roof, in lieu of the maximum height of 30 feet (Council Bill 107-20).
Meeting Location: Webex—County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
PAI Number: 09-0866
Tracking Number: MAJ-2019-00004
Proposal: 54 apartments.
Engineer: D.S.Thaler and Associates, Inc.
Until further notice and in compliance with Baltimore County COVID-19 safety guidelines, all Development Management Development Plan Hearings will be held virtually.
For additional information on the development hearing process please visit the Zoning and Development Hearings page.
To call in to the hearing, dial US Toll 1-415-655-0001, Access Code: 172 052 4317
Information: Contact Jerry S. Chen at jchen@baltimorecountymd.gov or 410-887-3321.

Development Plan Hearing—Brightview Perry Hall and Perry Hall Station 1st Material Amendment to the 3rd Refinement
Date and Time: Thursday, December 31, 10 a.m. to Noon
Property Location: 9655 Belair Road
Meeting Location: Webex—County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
PAI Number: 11-1114
Tracking Number: PUD-2020-00001-A
Proposal: Proposed add Lots 2, 2A and 2B into the Planned Unit Development boundary and construct 29 age-restricted single-family attached homes.
Webex—Virtual Hearing: To speak during the hearing, you must register at least two business days in advance by completing the online request form. You can join the meeting online or by phone. Use the registration link below to join the hearing online.
Join the hearing by phone: Call 1-415-655-0001; Access Code: 180 540 9205
Register for this hearing.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call 410-887-3391.

There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 5.