August 1, 2020 – Council District 5

  1. EPS Variances
  2. Planning Board Meetings
  3. Agricultural Land Preservation Advisory Board Public Hearing on the Adoption of Agricultural Easement Formula Regulation
  4. Comprehensive Zoning Map Process 2020
  5. Water Line Replacement in Towson
  6. Water Project in Carney
  7. Towson Improvements
  8. Stoneleigh-Anneslie Storm Water Project Resumes
  9. Water Improvements on Forge Road
  10. Water Line Rehabilitation: The Towson Fourth System
  11. The Future Fullerton Reservoirs
  12. Administrative Variances
  13. Development Meetings
  14. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 5

Planning Board Meetings

The board will meet virtually as follows:

  • No meetings scheduled for August.

Please check the Planning Board Meetings page for a link to the meeting, information on participating in the virtual meeting, the meeting agenda and any last-minute schedule changes.

Information: Contact Myles Muehlberger by phone at 410-887-3482 or by email at mmuehlberger@baltimorecountymd.gov.

Agricultural Land Preservation Advisory Board Public Hearing on the Adoption of Agricultural Easement Formula Regulation

The Department of Planning, in conjunction with the Baltimore County Agricultural Land Preservation Advisory Board, is providing notice of the intent to edit an existing regulation regarding the Agricultural Easement Formula as provided for in Sections 3-7-206 of the Baltimore County Code, 2015. The proposed revisions provide for an update of the formula used for the calculation of easement prices for applicants applying for the Fiscal Year 2021 County Agricultural Easement Cycle.

The Agricultural Land Preservation Advisory Board will hold a public hearing virtually on Wednesday, August 12 at 6:30 p.m. through Webex on the adoption of the Agricultural Easement Formula Regulation. Please visit the Agricultural Land Preservation Advisory Board Meetings page for a link to the meeting, information on participating in the virtual meeting, the meeting agenda and any last-minute schedule changes.

A copy of the proposed regulations may be obtained by visiting your public library or by contacting Wallace Lippincott at wlippincott@baltimorecountymd.gov or 410-887-3480.

Comments on the proposed regulations will be taken at the Public Hearing or you may provide written testimony prior to the hearing. To offer written testimony, please email comments to Wallace or mail them to: W. Lippincott, Jr., Baltimore County Department of Planning, 105 West Chesapeake Avenue, Suite 101, Towson, Maryland 21204.

Comments should be received prior to August 12, 2020.

Comprehensive Zoning Map Process 2020

The Comprehensive Zoning Map Process (CZMP) takes place every four years on an exact schedule specified in the County Code. Any citizen may request a zoning change on any property in Baltimore County, although the usual participants in the process are individual landowners, contract purchasers, community organizations, County staff, the Planning Board and the County Council.

The CZMP covers a period of approximately 12 months and results in zoning decisions that are reflected in a final log of issues. Ultimately, the County Council decides on each issue whether to retain the existing zoning or to enact a different zone(s) or district(s). Generally, each issue is a single property, but an issue might cover many adjoining properties and might even cover many hundreds of acres. The zoning on all properties that were not issues is reenacted without change.

The County Council will hold a special session for the final adoption on Tuesday, August 25, at 6 p.m. Additional information may be found on the County Council Schedule page.

For more information, please visit the CZMP page. If you have any questions, please contact the Department of Planning, 105 West Chesapeake Avenue, Suite 101, Towson, Maryland 21204. Call 410-887-3480 or email czmp2020@baltimorecountymd.gov.

Water Line Replacement in Towson

Baltimore County is replacing 18 feet of old cast-iron water main in Fairmount Avenue between York and Bosley Roads in Towson with a new 24-inch diameter line. The work includes the installation of a new valve and should begin in the summer. The project, which will cost $2.4 million, should be completed by the early spring of 2021.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Water Project in Carney

Baltimore County is replacing 1,000 feet of old cast-iron water pipe at Waltham Woods Road and Summit Avenue that has been breaking with regularity. The new line, which will be 16 inches in diameter, will cost $750,000. Work is 95 percent complete and is still on hold due to COVID-19. However, water line tie-ins to customers were scheduled to begin on July 9. Customers have been notified.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Towson Improvements

In cooperation with the Towson Row development, the Department of Public Works and Transportation and Transportation is improving sidewalks on Chesapeake Avenue between Washington Avenue and York Road. The work will be completed by the fall of 2021.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Stoneleigh-Anneslie Storm Water Project Resumes

The Department of Public Works and Transportation and Transportation is addressing storm water concerns in the Stoneleigh-Anneslie community and updating the 100-year-old drainage system. Baltimore County earmarked $1 million for the project in 2018. A system was designed last year and the County's contractor began work in February with the relocation of water lines. Work, however, was halted in the spring because of COVID-19 but is resuming with the installation of pipes and manholes on Kingston Road, Wardman Avenue, Marlborough Road, Avondale Road and a part of Regester Avenue. Water line relocations began on July 28. Working hours, traffic changes and parking impacts will be announced as the job progresses.

Information: Email the Bureau of Engineering and Construction, Storm Water Division at engineering@baltimorecountymd.gov.

Water Improvements on Forge Road

Baltimore County is replacing 2.64 miles of water line on Forge Road between Belair Road and Gaylord Street. The $3 million project, replacing old 12-inch diameter cast-iron pipes, began in November and is scheduled to be completed in the fall. It is 60 percent complete.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Water Line Rehabilitation: The Towson Fourth System

The Department of Public Works and Transportation and Transportation is replacing water lines in:

  1. Joppa Road between Old Harford Road and Drumwood Road
  2. Oakleigh Road between Joppa Road and White Oak Road
  3. Satyr Hill Road from Lowell Ridge Road to Harford Road

The project began in February 2018. It was scheduled to be completed by the spring of 2019 and will cost $6.7 million.

Information: Contact the Bureau of Engineering and Construction at engineering@baltimorecountymd.gov.

The Future Fullerton Reservoirs

The three-year-long construction of the Fullerton Reservoirs, costing $80.1 million, is 98 percent complete. Crews are currently building an ancillary building to facilitate water chlorination.

Information: Call the Bureau of Engineering and Construction, Water Design at 410-887-3783 or email engineering@baltimorecountymd.gov.

Administrative Variances

Administrative Variances Pending include requests for Administrative Variances pending before the Department of Permits, Approvals, and Inspections. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or Zoning Review at 410-887-3391.

There are no Administrative Variances pending at the time of publication of this newsletter. Please visit the Zoning calendar for changes in District 5.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

Development Plan Conference—Red Maple Place
Date and Time: Friday, August 7, 10 to 11 a.m.
Property Location: Entrance 407 East Joppa Road
Meeting Location: Webex—County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
PAI Number: 09-0866
Tracking Number: MAJ-2019-00004
Proposal: Proposed 56 apartments.
Meeting: Online or telephone via Webex. The project manager will provide County agency representatives, applicants and other registered interested parties wishing to monitor this meeting access information via email.
Attention: Until further notice all Development Plan Conference meetings will be held online. The public may request to monitor any Development Plan Conference meeting by registering with the project manager listed below no less than one week prior to the meeting date. Development Plan Conference meetings are not public hearings and access is at the discretion of Baltimore County.
Engineer: D.S. Thaler and Associates, Inc.
Project Manager: Jerry S. Chen
Information: Contact Jerry S. Chen at jchen@baltimorecountymd.gov or 410-887-3321.

Concept Plan Conference—The Preserve at Perry Hall
Date and Time: Tuesday, August 11, 11 a.m. to Noon
Property Location: Belair Road
Meeting Location: Webex—County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
PAI Number: 11-1182
Tracking Number: MAJ-2020-00004
Proposal: Forty-six single-family dwellings.
Meeting: Online or telephone via Webex. The project manager will provide County agency representatives, applicants and other registered interested parties wishing to monitor this meeting access information via email.
Attention: Until further notice all Concept Plan Conference meetings will be held online. The public may request to monitor any Concept Plan Conference meeting by registering with the project manager listed below no less than one week prior to the meeting date. Concept Plan Conference meetings are not public hearings and access is at the discretion of Baltimore County.
Engineer: Morris and Ritchie Associates, Inc.
Project Manager: Darryl D. Putty
Information: Contact Darryl D. Putty at ddputty@baltimorecountymd.gov or 410-887-3321.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call 410-887-3391.

There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 5.