February 15, 2022 - Council District 1
- EPS Variances
- Planning Board Meetings
- Cedar Branch North Fork Relief Sewer
- Water Main Replacement
- Sewer Rehabilitation in Catonsville
- Water Main Replacement
- Lower Powder Mill Interceptor Rehabilitation
- Washington Boulevard Water Main
- Patapsco Sewer Shed Basin 33 Relief Sewer
- Powder Mill Relief Sewer
- Development Meetings
- Zoning Hearings
EPS VARIANCES
The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.
Information: EPS Variances for District 1
PLANNING BOARD MEETINGS
The board will meet virtually through Webex as follows:
- Thursday, February 17, at 4:30 p.m.
- Immediately following the February 17 meeting, staff will provide Staff Recommendations on the Capital Improvement Program.
Please check the Planning Board page for links to the meetings, information on participating in the virtual meeting, the meeting agendas and any last-minute schedule changes.
Information: Contact Krystle Patchak by phone at 410-887-3482 or by email at kpatchak@baltimorecountymd.gov.
CEDAR BRANCH NORTH FORK RELIEF SEWER
Baltimore County has started work on the Cedar Branch North Fork Relief Sewer, located in the area of Johnnycake Road off of Rolling Road. Construction of 5,200 feet of 12-inch diameter pipe, costing approximately $3.4 million, will take 14 months.
Information: Email engineering@baltimorecountymd.gov.
WATER MAIN REPLACEMENT
Baltimore County is replacing 11,500 feet of eight-inch water main on Johnnycake Road south of Interstate 70. Preliminary work began in October. It is now four percent complete. Completion is expected in approximately two years. The cost is $3,152,179.
Information: Email engineering@baltimorecountymd.gov.
SEWER REHABILITATION IN CATONSVILLE
Baltimore County is rehabilitating more than 60,000 feet of sanitary sewer line in Catonsville. Work started in late August and is about 33 percent complete. The cleaning and lining project, which is expected to be finished before the end of next year, will cost $4 million. Crews from the County's contractor (SAK Construction) will be working in the neighborhood east of North Rolling Road and south of Baltimore National Pike (Route 40) in the heart of Catonsville. Residents can expect some minimal short-term disturbance as the work proceeds, and might be asked to move parked vehicles or reduce their waste water discharge for a few hours while sewer pipes are being relined.
Information: Call the Bureau of Engineering and Construction at 410-887-3531.
WATER MAIN REPLACEMENT
Baltimore County is replacing 7,000 feet of failing cast-iron water main on Maiden Choice Lane between Kenwood Avenue and Wilkens Avenue, and on Kenwood Avenue between Maiden Choice Lane and Wilkens Avenue. The new 12-inch and eight-inch diameter lines will cost $2.3 million. The project is about 80 percent finished and work is shut down for the winter.
Information: Email engineering@baltimorecountymd.gov.
LOWER POWDER MILL INTERCEPTOR REHABILITATION
Baltimore County began the rehabilitation of the Lower Powder Mill Sewer Interceptor in April. The line is 5,535 feet long and the project is expected to take more than a year. The estimated cost is $4,625,368 and it is about 29 percent finished. The contractor is currently doing preliminary work and waiting for materials.
Information: Email engineering@baltimorecountymd.gov.
WASHINGTON BOULEVARD WATER MAIN
Baltimore County is replacing an old 16-inch diameter water main on Washington Boulevard between Clark Boulevard and the CSX railroad tracks that has been prone to breaking. The project (1,200 feet of new pipe) is about 92 percent complete. The old pipe dates from 1950. The new pipe will cost $400,000.
Information: Email engineering@baltimorecountymd.gov.
PATAPSCO SEWER SHED BASIN 33 RELIEF SEWER
The Department of Public Works and Transportation is building a new sewer line south of Interstate 70 in Patapsco Valley State Park. The project, which will take a year to complete, will cost $10,967,777. It is 99 percent finished and will be completed when the final as-built plans have been received from the contractor.
Information: Email engineering@baltimorecountymd.gov.
POWDER MILL RELIEF SEWER
Baltimore County is investing $4,627,585 to improve the sewer system from Liberty Road to Gwynndale Avenue. Work began in September 2019 and is about 95 percent complete. Work is currently on hold until the Lower Powder Mill project is completed, releasing construction crews to complete road work.
Information: Email engineering@baltimorecountymd.gov.
DEVELOPMENT MEETINGS
Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These meetings are up-to-date as of the publication of this newsletter and subject to change.
Information: Call 410-887-3321.
There are no Development Meetings scheduled at the time of publication of this newsletter. Please visit the Development Management Calendar for changes in District 1.
ZONING HEARINGS
Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and subject to change.
Information: Call the Office of Administrative Law Judges at 410-887-3868 or Zoning Review at 410-887-3391.
There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 1.