Skip Navigation

Engineering Projects

The following is a list of current engineering projects by council district. This information is updated on a monthly basis. We also provide an interactive map to view the location of projects.

To receive an email with this information, you can subscribe to receive community updates.

Council District 1

  • Frederick Road StreetscapeBaltimore County is improving the south side of Frederick Avenue between Paradise Avenue and Maple Avenue. The work, costing $250,000, will include replacing dilapidated planters and adding trees.  For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Patapsco Sewer Shed Basin 33 Relief Sewer—Public Works recently began construction on a new sewer line south of I-70 in the Patapsco State Park. The project, which will take a year to complete, will cost $10,967,777. It is seven percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Powder Mill Relief Sewer—Baltimore County is investing $4,627,585 to improve the sewer system from Liberty Road to Gwynndale Avenue. Work began in September and is now about 11 percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water Project on Louisiana AvenueBaltimore County began installing 2,850 feet of new water line on Louisiana Avenue, from Annapolis Road to Baltimore Street, in November to replace an old, cast iron pipe. The project, expected to cost $700,000, will be completed in the spring of 2020. It is 90 percent complete. For more information contact the Bureau of Engineering at engineering@baltimorecountymd.gov

  • River Road Bridge Reconstruction—River Road Bridge (B-0184) was severely damaged during the May 2018 flood. River Road was immediately closed to traffic and contractors demolished the remaining structure in the weeks following the storm. The Department of Public Works planned a replacement bridge. Construction began in July and should be completed in late spring. The estimated cost is $1,800,000. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Louisiana Avenue—Baltimore County is adding curb and gutters along both sides of Louisiana Avenue from Washington Street to Baltimore Street. The work is expected to be completed before the end of the year. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

Council District 2

  • Deck Replacement on Circle Road BridgeBaltimore County’s contractors will begin work on the Circle Road Bridge over Roland Run in late spring. Construction was scheduled to start before the New Year, but was delayed to correct a problem with the decking material. Construction is expected to take about four weeks and traffic will not be interrupted during the work. Circle Road was in the news six years ago when the County replaced structural beams and when traffic was intermittently restricted during construction hours. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water in the Dumbarton Neighborhood of PikesvilleBaltimore County is relining and cleaning more than 16,000 feet of water line in 27 streets in Dumbarton. The project, managed in two phases, is about 50 percent complete and will cost $4,200,000. Work is currently on winter shutdown. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Lake Avenue Water Line Repair—Baltimore County is replacing a section of old cast-iron water pipe on Lake Avenue between Falls Road and Lakehurst Drive. Work began in January 2019. The old line, which dates from the 1920s, has failed frequently in recent years and will be replaced with ductile iron pipe. The project is estimated to cost $1,500,000. It is 99 percent complete and is expected to be completed by this summer. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

Council District 3

  • Water Project in Carney—Baltimore County is replacing 1,000 feet of old cast iron water pipe at Waltham Woods Road and Summit Avenue, which has been breaking with regularity. The new line, which will be 16 inches in diameter, will cost $850,000. Work is expected to begin in February and be completed in the summer. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water Main Replacement on York Road—Baltimore County is replacing a water main on York Road between Padonia Road and Wight Avenue. Contractors are replacing an old cast-iron main built in the 1930s, which has failed frequently in the past decade. The project, which began in July 2018, will cost about $14,000,000, and is expected to take about two years to complete. It is 88 percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

Council District 4

  • New Water Line on Reisterstown Road—Baltimore County is installing a new 36-inch diameter water line on Reisterstown Road between Rosewood Avenue and Pleasant Hill Road. Work on the new supply main, designed to serve the Owings Mills–Reisterstown area, is now 10 percent complete and is scheduled to be finished by the spring of 2021. The cost is about $9,000,000. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Old Court Road Bridge RehabilitationBaltimore County will rehabilitate the Old Court Road Bridge over Bens Run (B-0237) near Northwest Hospital this summer. The project, which will take about a year to complete and cost $2,000,000, will include replacing beams and sidewalks. During construction traffic will be maintained. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

Council District 5

  • Towson Sidewalk ImprovementsIn cooperation with the Towson Row development, the Department of Public Works is improving sidewalks on Chesapeake Avenue between Washington Avenue and York Road. The work will be undertaken this year. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water Improvements on Forge RoadBaltimore County is replacing 2.64 miles of water line on Forge Road, between Belair Road and Gaylord Street. The $3,000,000 project, replacing the old 12-inch diameter cast iron pipes, began in November 2019 and is scheduled to be completed this summer. It is now 20 percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Stoneleigh–Anneslie Storm Water Project—Baltimore County is addressing storm runoff concerns in the Stoneleigh–Anneslie community and is about to update the 100-year-old drainage system. Baltimore County has earmarked $1,000,000 for the project. The County's contractor was scheduled to begin work in early February with the relocation of water lines. Following the relocation, crews will install pipes and manholes on Kingston Road, Wardman Avenue, Marlborough Road, Avondale Road and a part of Regester Avenue. Construction is expected to be finished late this year and working hours, traffic changes and parking impacts will be announced as the job progresses. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water Line Rehabilitation of the Towson Fourth System—The Department of Public Works is replacing water lines in several areas: Joppa Road between Old Harford Road and Drumwood Road, Oakleigh Road between Joppa Road and White Oak Road, and Satyr Hill Road from Lowell Ridge Road to Harford Road. The project began in February 2018 and was expected to be completed in spring 2019. It is expected to cost $6,700,000. It is 98 percent complete. For information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Fullerton Reservoirs—The three-year long construction on the Fullerton Reservoirs costing $80,100,000, is currently 95 percent complete. Crews are currently building an ancillary building to facilitate water chlorination. We've provided additional information on the Fullerton Reservoirs (PDF), or you can send an email to the Bureau of Engineering Water Design at engineering@baltimorecountymd.gov or call 410-887-3783.

Council District 6

  • Brien Run Sewer Rehabilitation—Public Works is rehabilitating sewer lines in the Brien Run area south of Pulaski Highway. The project, anticipated to cost $7,000,000, should begin in March. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water on King Avenue—Baltimore County is investing $2,000,000 on King Avenue between Babikow Road and Philadelphia Road. Crews will install 6,500 feet of new, 12-inch diameter water line, which will replace an old pipe that has broken frequently. The project should begin in April and construction is expected to impact traffic: single-lane traffic from 9 a.m. to 3 p.m. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Oliver Beach Sewage Pumping Station—Renovations to the sewage pumping station project at 11206 Susquehanna Avenue in Middle River began in January 2019. It is now 51 percent complete and is expected to be finished this spring. Total cost is estimated at $2,585,114. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Bauernschmidt Manor Pumping Station—Upgrades to the Bauernschmidt Sewage Pumping Station began last July and will be finished by this summer. It is now 13 percent complete and expected to cost $2,137,554. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • New Water Mains for ParkvilleBaltimore County will install more than four miles of new water mains in Parkville beginning in December. The new ductile iron pipes will be located in an area bounded by Perring Parkway, Taylor Avenue, Harford Road and the Baltimore City line. The $5,600,000 project includes the reinstallation and relocation of 705 water service connections to water customers. It is now five percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Water Project on Back River Neck Road—Baltimore County is replacing 9,832 feet of cast-iron water pipe on Back River Neck Road from Hyde Park Road to Mizells Road starting in August. The old pipe, prone to frequent breaks and dating from the 1930s, will be replaced with ductile iron pipe. The project, costing about $4,150,000, is expected to be completed by this fall. It is now 47 percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Harewood Park Sewer Pumping Station—Baltimore County has begun renovating the Harewood Park Sewer Pumping Station at 12901 Princeton Road in Chase. Work on the $3,300,000 project officially began in July 2018. It is now 87 percent complete. For more information contact the Bureau of Engineering, engineering@baltimorecountymd.gov.    

  • Campbell Boulevard—Baltimore County is extending Campbell Boulevard from Bird River Road to Foxleigh Way. Construction of the $5,000,000 project began in October 2018 and is expected to take about a year and a half to complete. It should be open in late spring or early summer. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Fullerton ReservoirsThe Department of Public Works is completing the three Fullerton Reservoirs located within the area bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard. Construction is expected to take about three years and cost $80,100,000. The project is currently 95 percent complete. We've provided additional information on the Fullerton Reservoirs (PDF), or you can send an email to the Bureau of Engineering Water Design at engineering@baltimorecountymd.gov or call 410-887-3783.

  • Mohrs Lane Bridge—The Mohrs Lane Bridge (PDF) over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in March 2011 at no cost to Baltimore County, which assumed ownership and plans to rebuild the span. A new bridge is currently being designed with construction scheduled to begin by late 2021. This bridge will be part of the future Campbell Boulevard Corridor. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

Council District 7

  • Beachwood Road Pumping Station—Baltimore County began renovating the Beachwood Road Sewage Pumping Station in Dundalk almost a year ago. The project will be finished in March and cost $3,093,000. It is 98 percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • New Water Lines on Eastern Avenue—Baltimore County is replacing old cast iron water lines on Eastern Avenue (which have failed frequently) between Back River Bridge and Riverside Drive. Work on the new 24-inch mains began in mid-January and  is expected to be completed by this summer. It is five percent complete. The cost is expected to be $3,000,000. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Rosebank Avenue Pumping Station—The Department of Public Works is rehabilitating the Rosebank Avenue Sewage Pumping Station near North Point Boulevard in Dundalk. Work began late last year and is expected to be finished on January 30, 2020. The $2,300,000 project is 93 percent complete. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

  • Blenhurst Pumping Station—The Department of Public Works has started a major renovation of the Blenhurst Sewage Pumping Station at 8345 Bletzer Road. The project, now 47 percent complete, will cost $2,633,500 and was expected to be finished by December 2019. For more information, contact the Bureau of Engineering at engineering@baltimorecountymd.gov.

 
Revised February 19, 2020         

 

Did This Page Help?
Fields marked with * are required.
Page Rating*