Skip Navigation

Engineering Projects

The following is a list of current engineering projects by council district. This information is updated on a monthly basis. We also provide an interactive map to view the location of projects.

To receive an email with this information, you can subscribe to receive community updates.

Council District 1

  • Louisiana Avenue—Baltimore County is adding curb and gutters along both sides of Louisiana Avenue from Washington Street to Baltimore Street. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Bridge Repair on Ilchester Road—Public Works plans to begin repairs to the Ilchester Road Bridge (B-0056) over the Patapsco River in June. The repairs, costing about $300,000, will be made to both the deck and the superstructure and should take about three months. During the project, traffic will be maintained at all times, though there may be some single-lane closures. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Water Main Replacement in Wilkens Avenue Area—Baltimore County will begin replacing an old 16-inch diameter cast iron water line between Hilltop Road and Walker Avenue along with an eight-inch diameter line on Fairway Avenue in March. Both lines have had a history of frequent failures. The job, costing $1,500,000, is expected to be completed this summer. It is 80 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Powers Lane Water Line—Baltimore County is investing $3,500,000 to improve the water system in the Catonsville area. Three thousand feet of new water main is being constructed between the Catonsville pumping station and Nuwood Drive. The new main, which will be 36 inches in diameter, will improve the reliability of the system and should be finished this spring. It is now 75 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Dogwood Road Bridge—The Dogwood Road bridge (B-0347) over Dogwood Run will be closed for repairs for about six months. The $1,600,000 project is expected to begin in June and be completed by December. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Woodlawn Pedestrian Bridge—The Department of Public Works is completing a design to replace the former pedestrian bridge at Woodlawn High School (B-0166), which was removed in 2014. Construction of a new structure began in late February and will require about four months to complete. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

Council District 2

  • Jones Falls Structural Sewer Rehabilitation Phase 1—Baltimore County began rehabilitating 66,000 feet of sewer line last July throughout Council Districts 2 and 5. The project will last 18 months and will cost $3,393,583.60. It is now 43 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Water Pumping Station in Pikesville—Public Works began a major rehabilitation of the Pikesville Water Pumping Station inside the Beltway near Reisterstown Road in March 2016. The $5,900,000 project will take about two years to complete. The engineers note that the upgrade will include a completely new electrical system and replacement of two of the eight pumps. The project is 97 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

Council District 3

  • Galloway Avenue at York Road—Baltimore County is widening the south side of Galloway Avenue just west of York Road. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Greenpoint Road—Baltimore County is adding sidewalks on the south side of Greenpoint Road as it approaches Padonia Road. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

  • Shawan Road—The Department of Public Works is adding a lane to the south side of Shawan Road from the light rail to the old Verizon access drive. It is expected to be completed this summer. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Stablersville Road Bridge—A nine-foot long, concrete-slab bridge (B-0757) on Stablersville Road, just west of Graystone Road, is in need of repair and was reduced to one lane of traffic more than two years ago. The bridge is scheduled to be repaired and County engineers are scoping out options. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Gores Mill Road Bridges—Concrete bridges B-0136, B-0137,B-0138 and B-0346, which span Little Falls just south of the Morris Meadows Recreation Farm, were constructed more than 80 years ago and need replacement or rehabilitation. Work began last August and should be completed by the end of this year. The total cost is $3,600,000. The project is now 45 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

Council District 4

  • Owings Mills Reservoir—Baltimore County is painting the outside of the Owings Mills reservoir. The project, costing approximately $550,000, is scheduled to begin in July. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Old Court Road at Carlson Lane—Baltimore County is installing a traffic signal and decorative crosswalks on Old Court Road and Carlson Lane. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Dolfield Boulevard at Red Run Boulevard—Baltimore County is widening Dolfield Boulevard on the north side from Red Run Boulevard to Easter Court. For more information, contact the Bureau of Engineering, Department of Public Works at enginrng@baltimorecountymd.gov.

  • Dogwood Road Bridge—The Dogwood Road bridge (B-0347) over Dogwood Run will be closed for repairs for about six months. The $1,600,000 project is expected to begin in June and be completed by December. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Woodlawn Pedestrian Bridge—The Department of Public Works is completing a design to replace the former pedestrian bridge at Woodlawn High School (B-0166), which was removed in 2014. Construction of a new structure began in late February and will require about four months to complete. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Rolling Road Improvements—Baltimore County is widening Rolling Road to approximately 44 feet and four lanes and adding curbs, gutters and sidewalks, from Windsor Mill Road to Six Point Court. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

Council District 5

  • Stoneleigh-Anneslie Storm Water Project—Baltimore County is addressing storm runoff concerns in the Stoneleigh-Anneslie community east of York Road. County engineers are designing a solution to update the 100-year-old drainage system which is currently serving the community. Baltimore County has earmarked $1,000,000 for the project. During the process, County engineers and residents are meeting every second Friday of the month to discuss and clarify community issues. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Sewer Project on Towsontown Boulevard—Baltimore County is installing a major sewer line through Towsontown Boulevard. The project, estimated to cost $1,400,000, started early this year in the area of Emerson Road and has been moving toward Bosley Avenue. Completion is expected in the fall. Construction, scheduled between 9 a.m. and 3 p.m., has intermittently impacted traffic. Some night work is planned at the Osler Drive intersection in coming weeks. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Water Line Replacement in Campus Hills—Baltimore County is replacing an existing eight-inch diameter cast iron pipe in the Campus Hills area beginning in July. The project will cost $2,500,000. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Water Tank Rehabilitation—Baltimore County recently began structural repairs and interior and exterior painting of the Cub Hill Water Tank, which has a capacity of 1,000,000 gallons. The job, expected to cost about $800,000, is now about 15 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

  • Water Line Rehabilitation of the Towson Fourth System—The Department of Public Works is replacing water lines in several areas: (1) Joppa Road between Old Harford Road and Drumwood Road, (2) Oakley Road between Joppa Road and White Oak Road and (3) Satyr Hill Road from Lowell Ridge Road to Harford Road. The project began in February and is expected to be completed by the spring of 2019. It is expected to cost $6,700,000. It is eight percent complete. For information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Jones Falls Structural Sewer Rehabilitation Phase 1—Baltimore County began rehabilitating 66,000 feet of sewer line in July throughout Council Districts 2 and 5. The project will last a year and a half and will cost $3,393,583.60. It is now 43 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Herring Run Structural Sewer Rehabilitation Phase 1—Baltimore County is rehabilitating 81,000 feet of sewer line spread throughout Council Districts 5 and 6. Work recently began and has progressed about 47 percent toward completion. It is expected to be completed in 18 months and cost $4,640,123. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • New Water Main on Joppa Road—Baltimore County is replacing 7,000 feet of existing water pipe in Joppa Road, between Walther Boulevard and Belair Road. Construction began last August and is now 85 percent complete. The old pipe, which will be replaced with a new 12-inch diameter line, has failed frequently. The project is expected to cost $3,000,000 and require a year to complete. For more information, contact the Bureau of Engineering and Construction at enginrng@baltimorecountymd.gov.

  • Extension of Missing Curb, Sidewalk and Widening on Cross Road—Public Works is planning to fill in missing curbs and sidewalks on Cross Road between Chapel Road and Forge Road. Construction is expected to be done this year. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Fullerton ReservoirsThe County’s contractor broke ground on February 7, 2017 on the Fullerton Reservoirs—three are planned for the site. Construction is expected to take about three years and cost $80,100,000. The construction site is bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard. The project is currently 55 percent complete. We've provided additional information on the Fullerton Reservoirs (PDF), or you can send an email to the Bureau of Engineering Water Design at enginrng@baltimorecountymd.gov or call 410-887-3783.

Council District 6

  • Campbell Boulevard—Baltimore County is extending Campbell Boulevard from Bird River Road to Foxleigh Way. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Turkey Point Water Project—Baltimore County is replacing 16,000 feet of old cast iron water pipe on the Turkey Point Peninsula. The cast iron line has frequently failed in recent years and is being replaced with ductile iron pipe. The project, costing $5,500,000, is 95 percent complete and is expected to be completed by the end of this year. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Herring Run Structural Sewer Rehabilitation Phase 1—Baltimore County is rehabilitating 81,000 feet of sewer line spread throughout Council Districts 5 and 6. Work recently began and has progressed about 47 percent toward completion. It is expected to be completed in a year and a half and cost $4,640,123. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Fullerton Reservoirs—The County’s contractor broke ground on February 7, 2017 on the Fullerton Reservoirs—three are planned for the site. Construction is expected to take about three years and cost $80,100,000. The construction site is bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard. The project is currently 55 percent complete. We've provided additional information on the Fullerton Reservoirs (PDF), or you can send an email to the Bureau of Engineering Water Design at enginrng@baltimorecountymd.gov or call 410-887-3783.

  • Mohrs Lane Bridge—The Mohrs Lane Bridge (PDF) over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in March 2011 at no cost to Baltimore County, which assumed ownership and plans to rebuild the span. A new bridge is currently being designed with construction scheduled to begin in late 2019. This bridge will be part of the future Campbell Boulevard Corridor. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

Council District 7

  • 48th Street—Baltimore County is adding curb and gutter on the west side of 48th Street from Norman Avenue to Delvale Place. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Tickwood Road Sewer—Public Works is eliminating failing septic tanks for four properties at the end of Tickwood Road in Essex. The project consists of the construction of 2,100 feet of pressure sewer and four grinder pumps at a cost of $207,233.12. The date of notice to proceed will be May 1, 2018 and construction will be completed in July. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Marine Oaks Pumping Station—Baltimore County is upgrading the Marine Oaks Sewer Pumping Station in Essex. The improvements to the station are estimated to cost $1,584,537 and will take about a year to complete. Work began in January and is five percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Goodwood Avenue Water Project—Goodwood Avenue in Hyde Park will have 2,300 feet of water main replaced beginning in March. Installation of the new eight-inch diameter water main will require 100 working days to complete and cost $592,000. It is 25 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Beachwood Water Main Replacement—Baltimore County will begin replacing an eight-inch and a 12-inch diameter water line, both cast iron, which have frequently failed, on Rosebank Avenue, Edgewater Place, Glenhurst Road and Bletzer Road. The project, estimated to cost $1,500,000, began in late April and is scheduled to be finished by the spring of 2019. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Old Battle Grove Sewage Pumping Station—Public Works is renovating the Old Battle Grove Pumping Station in Dundalk. Work began in May 2017. The project is about 27 percent complete and estimated to cost $2,050,681. It should be completed August 22, 2018. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Thompson Boulevard Pumping Station—Public Works is renovating the Thompson Boulevard Sewage Pumping Station. Construction began last August and is expected to be completed on August 21, 2018. The project is expected to cost $2,248,000. It is about 33 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Peninsula Boulevard Pumping Station—Public Works is renovating the Peninsula Boulevard Pumping Station at 8401 Stansbury Road. Construction began last August and is expected to be completed November 7, 2018. The project is about 29 percent complete and is expected to cost $1,790,400. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Waldman Avenue Sewage Pumping Station—Baltimore County will renovate the Waldman Avenue Sewage Pumping Station at 7301 Waldman Avenue. Construction began last August and will take about a year to complete. The cost is estimated at $1,507,281 and the project is 31 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Quad Avenue Pumping Station Rehabilitation—Public Works is rehabilitating the Quad Avenue Pumping Station in Defense Heights. The project, which is expected to cost $2,240,000, is now 98 percent complete and should have been finished in October. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Wise Avenue Bridge—The Wise Avenue Draw Bridge can now be raised and lowered for water traffic with notice to the Department of Public Works. To request a bridge opening, call 410-887-8160, Monday through Friday, 8 a.m. to 3 p.m. or the Public Works Dispatch Number at 410-887-5210.

 
Revised April 23, 2018         

 

Did This Page Help?
Fields marked with * are required.
Page Rating*