Skip Navigation

Francis Scott Key Bridge Incident Updates
Watch the Recording of County Executive John A. Olszewski Jr. delivering the Proposed FY25 Budget Message

 December 15, 2018 – Council District 6

  1. EPS Variances
  2. Planning Board Meetings—None Scheduled
  3. Harewood Park Sewer Pumping Station
  4. Water Improvements in Victory Villa
  5. Campbell Boulevard
  6. Sewers: Herring Run Structural Rehabilitation Phase 1
  7. The Future Fullerton Reservoirs
  8. Mohrs Lane Bridge
  9. Homeless Persons' Memorial Service
  10. Administrative Variances
  11. Development Meetings
  12. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 6

Planning Board Meetings

Baltimore County Planning Board meetings are scheduled as follows:

  • None scheduled for December.

Information: Call the Department of Planning at 410-887-3211.

Harewood Park Sewer Pumping Station

Baltimore County has begun renovating the Harewood Park Sewer Pumping Station at 12901 Princeton Road in Chase. Work on the $3.3 million project officially began in July—it's now 11 percent complete—and will take about a year to finish.

Information: Email engineering@baltimorecountymd.gov.

Water Improvements in Victory Villa

Baltimore County is investing $2.5 million dollars in the Victory Villa area to replace aging, cast-iron water pipes in order to improve water quality, reliability and fire protection. The work, which will begin in January and should take a year to finish, will replace 9,700 feet of six-inch and eight-inch diameter cast-iron line.

Information: Email engineering@baltimorecountymd.gov.

Campbell Boulevard

Baltimore County is extending Campbell Boulevard from Bird River Road to Foxleigh Way. Construction of the $5 million project began in October and is expected to take about a year and a half to complete.

Information: Email engineering@baltimorecountymd.gov.

Sewers: Herring Run Structural Rehabilitation Phase 1

Baltimore County is rehabilitating 81,000 feet of sewer line spread throughout Council Districts 5 and 6. Work has progressed about 89 percent toward completion. It is expected to be completed in a year and a half and cost $4,640,123.

Information: Email engineering@baltimorecountymd.gov.

The Future Fullerton Reservoirs

On February 7, 2017, the Department of Public Works and Transportation and Transportation and Transportation broke ground on the Fullerton Reservoirs—three have been planned for the site. Construction is expected to take about three years and cost $80.1 million. Engineers estimate that the project is now about 76 percent complete. The construction site is bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard.

Information: Email engineering@baltimorecountymd.gov or call 410-887-3783.

Mohrs Lane Bridge

The Mohrs Lane Bridge (Bridge B-0143) over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in 2011 at no cost to Baltimore County, which has assumed ownership and plans to rebuild the span. A new bridge is currently being designed with construction scheduled to begin by late 2019. This bridge will be part of the future Campbell Boulevard Corridor.

Information: Email engineering@baltimorecountymd.gov.

Homeless Persons' Memorial Service

Join us on the longest night of the year, Friday, December 21, at 5 p.m. at Trinity Episcopal Church, 120 Allegheny Avenue in Towson, as we remember and honor the lives of those who have experienced homelessness in Baltimore County and passed away in 2018. If you know of any person who has been homeless and has passed away this year, please contact Terri Kingeter at 443-799-3760. This event is sponsored by Baltimore County Communities for the Homeless.

Administrative Variances

Administrative Variances pending include requests for Administrative Variances pending before the Department of Permits, Approvals and Inspections. These hearings up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or call Zoning Review at 410-887-3391.

There are no Administrative Variances scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 6.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

There are no Development Meetings scheduled at the time of publication of this newsletter. Please visit the Development Management Calendar for changes in District 6.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or call Zoning Review at 410-887-3391.

There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 6.