Skip Navigation

Francis Scott Key Bridge Incident Updates
Watch the Recording of County Executive John A. Olszewski Jr. delivering the Proposed FY25 Budget Message

December 1, 2019 – Council District 5

  1. EPS Variances
  2. Planning Board Meetings
  3. Design Review Panel Meeting
  4. Comprehensive Zoning Map Process (CZMP) 2020
  5. Stoneleigh-Anneslie Storm Water Project
  6. Water Improvements on Forge Road
  7. Improvements for the Campus Hills Pumping Station
  8. Water Line Replacement in Campus Hills
  9. Water Line Rehabilitation: The Towson Fourth System
  10. The Future Fullerton Reservoirs
  11. Administrative Variances
  12. Development Meetings
  13. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 5

Planning Board Meetings

Baltimore County Planning Board meetings are scheduled as follows:

  • None scheduled for December

Information: Contact Myles Muehlberger by phone at 410-887-3482 or by email at mmuehlberger@baltimorecountymd.gov.

Design Review Panel Meeting

The Design Review Panel meeting will be held on Wednesday, December 11, at 6 p.m. in Room 104 of the Jefferson Building, 105 West Chesapeake Avenue in Towson.

Information: Contact Jenifer Nugent at 410-887-3480 or jnugent@baltimorecountymd.gov.

Comprehensive Zoning Map Process 2020

The Comprehensive Zoning Map Process (CZMP) takes place every four years on an exact schedule specified in the County Code. Any citizen may request a zoning change on any property in Baltimore County, although the usual participants in the process are individual landowners, contract purchasers, community organizations, County staff, the Planning Board and the County Council.

The CZMP covers a period of approximately 12 months and results in zoning decisions that are reflected in a final log of issues. Ultimately, the County Council decides on each issue whether to retain the existing zoning or to enact a different zone(s) or district(s). Generally, each issue is a single property, but an issue might cover many adjoining properties and might even cover many hundreds of acres. The zoning on all properties that were not issues is reenacted without change.

View a list of public hearing dates and locations. For more information, please visit the CZMP page.

If you have any questions, please contact the Department of Planning, 105 West Chesapeake Avenue, Suite 101, Towson, Maryland 21204. Call 410-887-3480 or email czmp2020@baltimorecountymd.gov.

Stoneleigh-Anneslie Storm Water Project

The Department of Public Works and Transportation and Transportation and Transportation and Transportation is addressing storm water concerns in the Stoneleigh-Anneslie community and is about to update the 100-year-old drainage system. Baltimore County earmarked a million dollars for the project in 2018 and the County's contractor will begin work in December or early 2020 with the relocation of water lines. Following the relocation, crews will install pipes and manholes on Kingston Road, Wardman Avenue, Marlborough Road, Avondale Road and a part of Regester Avenue. Construction is expected to be finished late next year and working hours, traffic changes and parking impacts will be announced as the job progresses.

Information: Email the Bureau of Engineering and Construction, Storm Water Division at engineering@baltimorecountymd.gov.

Water Improvements on Forge Road

Baltimore County plans to replace 2.64 miles of water line on Forge Road between Belair Road and Gaylord Street. The $3 million project, replacing the old 12-inch diameter cast-iron pipes, began in November and is scheduled to be completed in the summer of 2020.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Improvements for the Campus Hills Pumping Station

The Department of Public Works and Transportation and Transportation and Transportation and Transportation is improving the Campus Hills Sewage Pumping Station at 1002 Southwick Court in Campus Hills. Work on the $2.54 million project began in September 2018 and is 99 percent complete. It is scheduled for completion is April 2020.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Water Line Replacement in Campus Hills

Baltimore County is replacing an existing eight-inch diameter cast-iron pipe in the Campus Hills area. Construction began in June 2018 and is about 95 percent complete. The project will cost $2.5 million.

Information: Contact the Bureau of Engineering and Construction at engineering@baltimorecountymd.gov.

Water Line Rehabilitation: The Towson Fourth System

The Department of Public Works and Transportation and Transportation and Transportation and Transportation is replacing water lines in:

  1. Joppa Road between Old Harford Road and Drumwood Road
  2. Oakleigh Road between Joppa Road and White Oak Road
  3. Satyr Hill Road from Lowell Ridge Road to Harford Road

The project began in February 2018. It was scheduled to be completed by the spring of 2019 and will cost $6.7 million. It is 98 percent complete.

Information: Contact the Bureau of Engineering and Construction at engineering@baltimorecountymd.gov.

The Future Fullerton Reservoirs

The three-year long construction of the Fullerton Reservoirs, costing $80.1 million, is now 91 percent complete. Crews are currently building an ancillary building to facilitate water chlorination.

Information: Call the Bureau of Engineering and Construction, Water Design at 410-887-3783 or email engineering@baltimorecountymd.gov.

Administrative Variances

Administrative Variances Pending include requests for Administrative Variances pending before the Department of Permits, Approvals, and Inspections. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or Zoning Review at 410-887-3391.

Administrative Variances—3931 Miller Road
Date and Time: Monday, December 9, 8:30 a.m. to 4:30 p.m.
Case Number: 2019-0513-A
Property Location: East side of Miller Road, 41 feet to the intersection of Pepper Hill Road
Legal Owners: Thomas and Erica Wienholt
Administrative Variance to permit a setback of 22 feet in lieu of the required 30 feet for an open porch to extend into a rear yard.
Closing Date: Monday, December 9, 4:30 p.m., 111 West Chesapeake Avenue, Room 111, Towson, Maryland 21204
Information: Contact the Zoning Office at 410-887-3391.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

Development Review Committee—The Villages of White Marsh PUD
Date and Time: Tuesday, December 3, 2 to 3 p.m.
Property Location: West of Perry Hall Boulevard
Meeting Location: County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
DRC Number: 120319C
PAI Number: 140496
Tracking Number: DRC-2019-00162
Request: The request is to revise the orientation of the single-family attached dwellings located along Dieter Drive and Arcola Road from a rear load product to a front load.
Information: Contact Lloyd Moxley at lmoxley@baltimorecountymd.gov or 410-887-3321.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call 410-887-3391.

Zoning Hearings—8116 Redstone Road
Date and Time: Monday, December 9, 11 a.m. to Noon
Case Number: 2019-0497-SPHA
Property Location: East side of Redstone Road, west of Yellowstone Road
Legal Owners: Joseph Espodito
Special Hearing for an amendment to the Final Development Plans for Fox Creek Farm with respect to Lot five only. Variance to allow a side yard setback of 18 feet in lieu of the required 50 feet for a principal dwelling.
Hearing Location: Jefferson Building, 105 West Chesapeake Avenue, Room 205, Towson, Maryland 21204
Information: Contact the Zoning Office at 410-887-3391.