Skip Navigation

March 1, 2019 – Council District 5

  1. EPS Variances
  2. Planning Board Meetings
  3. Landmarks Preservation Commission Meeting
  4. Water Improvements on Forge Road
  5. Improvements for the Campus Hills Pumping Station
  6. Water Line Replacement in Campus Hills
  7. Towsontown Boulevard and Osler Drive
  8. Stoneleigh-Anneslie Storm Water Project
  9. Water Line Rehabilitation: The Towson Fourth System
  10. Sewers: Jones Falls Structural Rehabilitation Phase 1
  11. Sewers: Herring Run Structural Rehabilitation Phase 1
  12. Extension of Missing Curb, Sidewalk-Widening on Cross Road
  13. The Future Fullerton Reservoirs
  14. Administrative Variances
  15. Development Meetings
  16. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 5

Planning Board Meetings

Baltimore County Planning Board meetings are scheduled as follows:

  • Thursday, March 7, at 4 p.m., in Room 104, Jefferson Building, 105 West Chesapeake Avenue in Towson
  • Thursday, March 21, at 4 p.m., in Room 104, Jefferson Building, 105 West Chesapeake Avenue in Towson

Information: Contact Ngone Seye Diop by phone at 410-887-3482 or by email at nseyediop@baltimorecountymd.gov.

Landmarks Preservation Commission Meeting

The Landmarks Preservation Commission meeting will be held on Thursday, March 14, at 6 p.m., in Room 104 of the Jefferson Building, 105 West Chesapeake Avenue in Towson.

Information: Contact Teri Rising at 410-887-3495 or histpres@baltimorecountymd.gov.

Water Improvements on Forge Road

Baltimore County will begin work on 2.64 miles of water line replacement on Forge Road. The project is scheduled to begin in July.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Improvements for the Campus Hills Pumping Station

The Department of Public Works and Transportation and Transportation is improving the Campus Hills Sewage Pumping Station at 1002 Southwick Court in Campus Hills. Work on the $2.5 million project began in September and is seven percent complete.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Water Line Replacement in Campus Hills

Baltimore County is replacing an existing eight-inch diameter cast-iron pipe in the Campus Hills area. Construction began in June and is about 55 percent complete. The project will cost $2.5 million.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Towsontown Boulevard and Osler Drive

The Department of Public Works and Transportation and Transportation has completed the Towson Run Relief Sewer through Towsontown Boulevard. Paving is scheduled for the spring.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Stoneleigh-Anneslie Storm Water Project

Baltimore County is addressing storm runoff concerns in the Stoneleigh-Anneslie community east of York Road. County engineers have designed a solution to update the 100-year-old drainage system that is currently serving the community. The County has earmarked $1 million for the project. Construction is expected to begin in the summer.

Information: Email the Department of Public Works, Bureau of Engineering, Storm Water Division at engineering@baltimorecountymd.gov.

Water Line Rehabilitation: The Towson Fourth System

The Department of Public Works and Transportation and Transportation is replacing water lines in:

  1. Joppa Road between Old Harford Road and Drumwood Road
  2. Oakleigh Road between Joppa Road and White Oak Road
  3. Satyr Hill Road from Lowell Ridge Road to Harford Road

The project began in February 2018. It will be completed by the spring and will cost $6.7 million. It is 88 percent complete.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Sewers: Jones Falls Structural Rehabilitation Phase 1

Baltimore County began rehabilitating 66,000 feet of sewer line in July 2017 throughout Council Districts 2 and 5. The project will last a year and a half and will cost $3,393,583.60. It is now 93 percent complete.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Sewers: Herring Run Structural Rehabilitation Phase 1

Baltimore County has been rehabilitating 81,000 feet of sewer line spread throughout Council Districts 5 and 6. Work has progressed rapidly and is about 99 percent toward completion. It is expected to be completed in a year and a half and cost $4,640,123.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

Extension of Missing Curb, Sidewalk-Widening on Cross Road

The Department of Public Works is planning to fill in missing curbs and sidewalks on Cross Road between Chapel Road and Honeygo Boulevard.

Information: Email the Department of Public Works at engineering@baltimorecountymd.gov.

The Future Fullerton Reservoirs

The County’s contractor received a “notice to proceed” in January 2017 and the Department of Public Works and Transportation and Transportation broke ground on February 7, 2017 on the Fullerton Reservoirs—three are planned for the site. Construction is expected to take about three years and cost $80.1 million. The construction site is bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard. Engineers estimate that the project is now 83 percent complete.

Information: Call the Bureau of Engineering, Water Design at 410-887-3783 or email engineering@baltimorecountymd.gov.

Administrative Variances

Administrative Variances Pending include requests for Administrative Variances pending before the Department of Permits, Approvals, and Inspections. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or Zoning Review at 410-887-3391.

There are no Administrative Variances pending at the time of publication of this newsletter. Please visit the Zoning calendar for changes in District 5.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

There are no Development Meetings scheduled at the time of publication of this newsletter. Please visit the Development Management Calendar for changes in District 5.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and are subject to change.

Information: Call 410-887-3391.

There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 5.