Skip Navigation

Francis Scott Key Bridge Incident Updates
Watch the Recording of County Executive John A. Olszewski Jr. delivering the Proposed FY25 Budget Message

October 1, 2019 – Council District 1

  1. EPS Variances
  2. Planning Board Meetings
  3. Design Review Panel Meeting
  4. Landmarks Preservation Commission Meeting
  5. Pedestrian and Bicycle Advisory Committee Subcommittee Meeting
  6. Comprehensive Zoning Map Process 2020 Has Begun
  7. Water Project on Louisiana Avenue
  8. River Road Bridge Reconstruction
  9. Louisiana Avenue
  10. New Water Line on Powers Lane
  11. Administrative Variances
  12. Development Meetings
  13. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 1

Planning Board Meetings

Baltimore County Planning Board meetings are scheduled as follows:

  • Thursday, October 3, at 4:30 p.m., in Room 104, Jefferson Building, 105 West Chesapeake Avenue in Towson
  • Thursday, October 17, at 5 p.m., in Room 104, Jefferson Building, 105 West Chesapeake Avenue in Towson

Information: Contact Myles Muehlberger by phone at 410-887-3482 or by email at mmuehlberger@baltimorecountymd.gov.

Design Review Panel Meeting

The Design Review Panel meeting will be held on Wednesday, October 2, at 6 p.m. in Room 104 of the Jefferson Building, 105 West Chesapeake Avenue in Towson.

Information: Contact Jenifer Nugent at 410-887-3480 or jnugent@baltimorecountymd.gov.

Landmarks Preservation Commission Meeting

The Landmarks Preservation Commission meeting will be held on Thursday, October 10, at 6 p.m., in Room 104 of the Jefferson Building, 105 West Chesapeake Avenue in Towson.

Information: Contact Taylor Bensley at 410-887-3495 or histpres@baltimorecountymd.gov.

Pedestrian and Bicycle Advisory Committee Subcommittee Meeting

The Pedestrian and Bicycle Advisory Committee subcommittee meeting will be held on Tuesday, October 15, at 4 p.m. in Room 104 of the Jefferson Building, 105 West Chesapeake Avenue in Towson.

Information: Call Jessie Bialek at 410-887-3211.

Comprehensive Zoning Map Process 2020 Has Begun

The Comprehensive Zoning Map Process (CZMP) takes place every four years on an exact schedule specified in the County Code. Any citizen may request a zoning change on any property in Baltimore County, although the usual participants in the process are individual landowners, contract purchasers, community organizations, County staff, the Planning Board and the County Council.

The CZMP covers a period of approximately 12 months and results in zoning decisions that are reflected in a final log of issues. Ultimately, the County Council decides on each issue whether to retain the existing zoning or to enact a different zone(s) or district(s). Generally, each issue is a single property, but an issue might cover many adjoining properties and might even cover many hundreds of acres. The zoning on all properties that were not issues is reenacted without change.

CZMP public filing ends at 4:30 p.m. on Tuesday, October 15. Applications are available online. Information about filing fees and public hearing dates are posted, as well.

If you have any questions, please contact the Department of Planning, 105 West Chesapeake Avenue, Suite 101, Towson, Maryland 21204. Call 410-887-3480 or email czmp2020@baltimorecountymd.gov.

For more information, please visit the CZMP page.

Water Project on Louisiana Avenue

This fall, Baltimore County will begin installing 2,850 feet of new water line on Louisiana Avenue from Annapolis Road to Baltimore Street to replace an old cast-iron pipe. The project, expected to cost $700,000, will be completed in the spring.

Information: Email engineering@baltimorecountymd.gov or call the Division of Highway Design at 410-887-3739.

River Road Bridge Reconstruction

River Road Bridge (Bridge B-0184) was severely damaged during the May 2018 flood that hit Baltimore and Howard counties. River Road was immediately closed to traffic and contractors then demolished the remaining structure in the weeks following the storm. The Department of Public Works and Transportation planned a replacement bridge. Construction began in July and should be completed early next year. The estimated cost is $1.8 million.

Information: Email engineering@baltimorecountymd.gov.

Louisiana Avenue

Baltimore County is adding curbs and gutters along both sides of Louisiana Avenue in English Consul from Washington Street to Baltimore Street. The work is expected to begin following water utility work that will begin in the fall and take three to four months to complete.

Information: Email engineering@baltimorecountymd.gov.

New Water Line on Powers Lane

Baltimore County is investing $3.5 million to improve the water system in the Catonsville area. Three thousand feet of new water main is being constructed between the Catonsville pumping station and Nuwood Drive. The new main, which will be 36 inches in diameter, will improve the reliability of the system. The project is 99 percent complete.

Information: Email engineering@baltimorecountymd.gov.

Administrative Variances

Administrative Variances Pending include requests for Administrative Variances pending before the Department of Permits, Approvals and Inspections. These variances are up-to-date as of the publication of this newsletter and subject to change.

There are no Administrative Variances pending at the time of publication of this newsletter. Please visit the Zoning calendar for changes in District 1.

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee and Hearing Officers Hearings. These meetings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call 410-887-3321.

Development Review Committee—Chadwick Manor Townhouse
Date and Time: Tuesday, October 1, 2 to 3 p.m.
Property Location: 23 Doray Court
Meeting Location: County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
DRC Number: 100119A
Tracking Number: DRC-2019-00129
Request: The project proposal includes the replacement of the existing pool house, pool, and patio with a new clubhouse.
Information: Contact Jan M. Cook at jmcook@baltimorecountymd.gov or 410-887-3321.

Development Review Committee—Barton Brands Exterior Tank Farm
Date and Time: Tuesday, October 8, 2 to 3 p.m.
Property Location: 2200 Monumental Road
Meeting Location: County Office Building, Room 123, 111 West Chesapeake Avenue, Towson, Maryland 21204
DRC Number: 100819A
Tracking Number: DRC-2019-00130
Request: The request is to add a pump house and exterior tank farm adjacent to the bottling plant building.
Information: Contact Jan M. Cook at jmcook@baltimorecountymd.gov or 410-887-3321.

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances and other issues before the Office of Administrative Hearings of Baltimore County. These hearings are up-to-date as of the publication of this newsletter and subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or Zoning Review at 410-887-3391.

There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Zoning Calendar for changes in District 1.