York Road

Image of the water pipe installation on York Road.

Baltimore County’s contractors are replacing 9,500 feet of old water line in York Road, between Ridgely Road and Padonia Road. The new 24-inch line, double the diameter of the old line, is expected to cost $5 million and take one to three years to install. The project, according to County engineers, is designed “to build redundancy into the system". The County’s contractor, Burgermeister Bell, started the project in April 2010 and may be finished by this summer. The project is 98 percent complete.

For more information contact the Bureau of Engineering and Construction at enginrng@baltimorecountymd.gov.

Revised March 27, 2014