Montrose Avenue Pumping Station

 Image showing location of Montrose Avenue pump station.

Public Works plans extensive improvements to the Montrose Avenue sewage pumping station this year by expanding the facility and enhancing the landscape. The project, which engineers say will take about a year to complete, was started in late September. It is expected to be complete by April 2, 2014 (not March 27 as reported last month). The project will cost about $1 million.

For more information contact Public Works at enginrng@baltimorecountymd.gov

Revised March 27, 2014