Skip Navigation

Engineering Projects

Following is a list of current engineering projects by council district. This information is updated on a monthly basis. We have also provided a new interactive map to view the location of projects.

To receive an email with this information, you can subscribe to receive community updates.

Council District 1

  • Nine Miles of Sewer Rehabilitation near Route 40 – Baltimore County is rehabilitating 46,000 feet of sewer line in two sections. The first lies south of Route 40, between Winters Lane and Ingleside Avenue and the second is between Academy Road and the Baltimore City line. The project, designated West Low Level Sewer Rehabilitation Level One and Three, will cost $2,888,960 and should be completed by June 2017. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Dead Run Sewer Shed Basin Rehabilitation near Rolling Road – Baltimore County is rehabilitating 27,000 feet of sewer line west of Rolling Road between Clays Lane and Security Boulevard. The project, which should be complete by June 2017, will cost $1,820,121. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Southwestern Boulevard Water Project – Public Works will replace 2,500 feet of 16-inch diameter water line on Southwestern Boulevard beginning in March. The new ductile iron pipe will run from Francis Avenue to Clark Boulevard. The new line, costing $3,400,000, will replace an old main which has been prone to breaking. The project is six percent complete. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

Council District 2

  • Water Main Replacement in Sudbrook Park – Public Works is replacing 15,000 feet of water main in the Sudbrook Park area. The project is estimated to cost $3,200,000. It began in mid-March and is expected to be finished in late 2017. It is 65 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

  • Water Main Replacement in Towson – Public Works is replacing 2,500 feet of water main on North Bend Road, Debaugh Avenue and Round Oak Avenue. Work began in June and should be finished by the fall. The project is expected to cost $800,000. It is about 25 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

  • Water Pumping Station in Pikesville – Public Works began a major rehabilitation of the Pikesville Water Pumping Station, inside the Beltway and near Reisterstown Road, in March. The $5,900,000 million project will take about two years to complete. The engineers note that the upgrade will include a completely new electrical system and a replacement of two of the eight pumps. The project is eight percent complete. For more information, Department of Public Works at enginrng@baltimorecountymd.gov

  • Water Project on Reisterstown Road – Baltimore County is installing 2,500 feet of 24-inch and 36-inch diameter water line on Reisterstown Road, between Rosewood Lane and Garrison View Road. The project, costing $4,000,000, began in November and is expected to be completed this December. It is 45 percent complete and most of the construction will be done at night. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Valley Village Pumping Station – The Valley Village Sewage Pumping Station at 201 Greenspring Valley Road is being rehabilitated. Work began in early October 2014 and should be finished by the end of August, though the project deadline is September 20. The project is 97 percent complete and the cost is estimated at $1,942,800. For more information contact Public Works at enginrng@baltimorecountymd.gov

Council District 3

  • Sunnybrook Water Renovations – Sunnybrook’s water facilities are being given a major renovation. In February crews began replacing pipes and motor controls, rehabilitating the tank and expanding the treatment process which now serves about 100 customers. The $2,520,000 project is expected to take about 14 months and is eight percent complete. For more information, contact the Department of Public Works at enginrng@baltimorecountymd.gov

    Valley Mill Road Bridge to Close for Repairs – Public Works plans to close Valley Mill Road Bridge (Bridge Number B-0160) for six to eight weeks beginning sometime this fall in order to replace the bridge deck. The bridge, which spans Little Falls, was built in 1975 with a steel deck. The deck will be replaced with an open-grid deck which should lengthen the life of the structure. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Ensor Road Bridge – The Ensor Road Bridge (Bridge B-0158) over Third Mine Branch near Stablersville is being replaced. The span was closed in April, work started in May and it should be reopened in October. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

  • Stablersville Road Bridge – A nine-foot long, concrete-slab bridge (B-0757) on Stablersville Road, just west of Graystone Road, is in need of repair and has been reduced to one lane of traffic. The bridge is scheduled to be repaired this summer.  For more information, contact Public Works at enginrng@baltimorecountymd.gov.

  • Gores Mill Road Bridge – Public Works closed bridge B-0138 over Little Falls at the end of April, 2015 because of deteriorating concrete. The bridge had been scheduled for replacement in 2017. For more information see the next project information, or contact Public Works at enginrng@baltimorecountymd.gov.

  • Other Gores Mill Road Bridges – The concrete bridges, which span Little Falls just south of the Morris Meadows Recreation Farm, were constructed more than 80 years ago and three of the four have reached the end of their useful life. One can be rehabilitated. Bridges B-0136, B-0138 and B-0346 are scheduled for replacement and new structures are currently being designed. Construction is anticipated for the spring of 2017. Bridge B-0137, immediately adjacent to Bridge B-0138, will be widened for traffic safety. Both Federal and County funds are being used on this $2,600,000 project. The acquisition of necessary rights-of-way began in June 2014. One right-of-way adjacent to Bridge B-0346 is still pending. For more information, contact Public Works at enginrng@baltimorecountymd.gov.

Council District 4

  • Fieldstone Pumping Station in Randallstown – Baltimore County is investing $1,601,272 to improve the Fieldstone Sewage pumping Station located at 8808 Stonehaven Road in Randallstown. Work began last October and is expected to be completed this October. It is now 83 percent complete. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Sewer Work in the Gwynns Falls Basin – Two large sewer rehabilitation projects are proceeding in the Gwynns Falls Basin area. One is the restoration of lines on Liberty Road from Courtleigh Drive to the Milford Mill area. The other is near Gwynn Oak Avenue. 50,000 feet of pipe is being rehabilitated at a cost of $5,208,563. Both projects together are 88 percent complete. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Dead Run Structural Rehabilitation – Following a television examination of sewer lines in the Dead Run Sewer Area, Public Works began a selective rehabilitation of pipe in November. The work, which is a re-lining process, will cost $2,376,229. It is now 82 percent complete and should be finished by November. For more information contact Public Works at enginrng@baltimorecountymd.gov.

  • Rolling Road Improvements – Baltimore County is widening to approximately 44 feet and four lanes and adding curbs, gutters and sidewalks to Rolling Road, from Windsor Mill Road to Orchard Avenue, in a long-term improvement project which began in January 2014 with utility relocation work. For more information contact Public Works at enginrng@baltimorecountymd.gov.

Council District 5

  • Gunpowder Outfall Sewer Transition Structure Repair – Baltimore County is rehabilitating a manhole in Perry Hall, near Soth Avenue and Yvonne. The work, which began in June, is expected to be completed by September 16 and cost $200,000. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Herring Run Basin 31 – A sewer line rehabilitation project is underway in the Ridgeleigh Community, also known as “The Oaks”, situated near Loch Raven Boulevard and Joppa Road. The job will repair 23,000 feet of sewer line, cost $2,043,609 and is expected to be completed in December. It is 70 percent complete. For more information contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Fullerton Reservoirs – Public Works held a workshop on the future Fullerton Reservoir Construction Project in November, 2014. The $78-million-dollar project was advertised in June, and Public Works expects to break ground in the fall or early winter on a site bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard. Engineers are currently working on environmental permits for the project and once the project has begun, regular progress reports will be posted. For more information (PDF), call the Department of Public Works, Bureau of Engineering (Water Design) at 410-887-3783 or email enginrng@baltimorecountymd.gov.

  • Water Improvements in Carney – Utility crews began replacing an old water line running under Harford Road in 2014. A new 12-inch replacement line will be installed on Harford Road between Cub Hill Road and a point 250 feet north of Joppa Road. Construction of the 7,500 feet of line will cost $3,800,000 and should be finished this fall. Crews have now completed about 97 percent of the project. For more information contact Public Works at enginrng@baltimorecountymd.gov.

Council District 6

  • Water Line Replacement in Overlea – Baltimore County will replace 2,300 feet of 12-inch diameter water line running from Kenwood Avenue at Dale Avenue, to the City line. The $100,100,000 project is expected to be completed in about 10 months. It is 92 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Sue Creek Landing Pumping Station –The Sue Creek Landing Sewage Pumping Station, located on Sue Avenue in Turkey Point, is being rehabilitated. The contractor began last June and should be finished in September. The rehabilitation project is about 75 percent complete and will cost $1,765,830. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Fullerton Reservoirs – Public Works held a workshop on the future Fullerton Reservoir Construction Project in November, 2014. The $78-million-dollar project be advertised in June, and Public Works expects to break ground in the fall or early winter on a site bounded by Ridge Road, Bucks School House Road and Perry Hall Boulevard. Once the project has begun, regular progress reports will be posted. For more information (PDF), call the Department of Public Works, Bureau of Engineering (Water Design) at 410-887-3783 or email enginrng@baltimorecountymd.gov.

  • Mohrs Lane Bridge (PDF) – The Mohrs Lane Bridge over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in March 2011 at no cost to Baltimore County, which assumed ownership and plans to rebuild the span. A new bridge is currently being designed with construction scheduled to begin by early 2017. This bridge will be part of the future Campbell Boulevard Corridor. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov.

  • Water Improvements near Mohrs Lane –As part of the bridge project, the Department of Public Works is installing a new water connection between mains on Philadelphia Road and Pulaski Highway. The job, which calls for 2,000 feet of line, is expected to cost about $350,000 and be advertised this fall. For details, contact the Department of Public Works, at enginrng@baltimorecountymd.gov

Council District 7

  • Quad Avenue Pumping Station Rehabilitation – Public Works is rehabilitating the Quad Avenue Pumping Station in Defense Heights. The project, which is expected to cost $2,240,000, is now 10 percent complete and should be finished by February. For more information contact Public Works at enginrng@baltimorecountymd.gov

  • Water Line Replacement in Sollers Point – Public Works began replacing 3,375 feet of six-inch diameter water line with eight-inch line in Dundalk this month, and will transfer 81 water services or connections to the new line. The work will improve lines on Maryland Avenue, Broening Highway, Avon Avenue, Center Avenue and Patapsco Avenue. The project is expected to be finished in the fall. It is 20 percent complete. For more information, contact the Bureau of Engineering at enginrng@baltimorecountymd.gov

  • Dundalk Water Lines – In October 2013, the Department of Public Works began renovating 90,000 feet of water lines in Dundalk. Conduits which lie between North Point Road, Merritt Boulevard, Stansbury Road and Bear Creek are being cleaned and lined with cement to improve water quality and fire protection. This is a long-term project, is expected to take three years and cost $4.3 million. Crews have completed about 93 percent of the project and should finish this year. For more information contact Public Works at enginrng@baltimorecountymd.gov.

  • Wise Avenue Bridge – The Wise Avenue Draw Bridge can now be raised and lowered for water traffic with notice to the Department of Public Works. To request a bridge opening, call 410-887-8160, Monday through Friday, 8 a.m. to 3 p.m. or the Public Works Dispatch Number at 410-887-5210.

 

Revised August 19, 2016        

Did This Page Help?
Fields marked with * are required.
Page Rating*