March 14, 2014 - Council District 6

  1. EPS Variances
  2. Planning Board Meetings Canceled
  3. Pasturing and Stabling of Livestock – Public Input Meeting
  4. Sewer Improvements
  5. Twin Rivers Pumping Station
  6. Cowenton Avenue Sewers
  7. Wye Road Pumping Station
  8. Hawthorne II Pumping Station
  9. Campbell Boulevard Phase 2
  10. Bengies Sewer Pumping Station
  11. Mohrs Lane Bridge
  12. Administrative Variances
  13. Development Meetings
  14. Zoning Hearings

EPS Variances

The Department of Environmental Protection and Sustainability (EPS) publishes a list of the environmental administrative variance requests along with their status. The requests are listed by County Council District.

Information: EPS Variances for District 6

Back to top

Planning Board Meetings Canceled

The Baltimore County Planning Board meetings schedule is as follows:

  • Thursday, March 20, at 4 p.m. in Room 104, Jefferson Building, 105 W. Chesapeake Avenue, in Towson.

Information: Email Curtis Murray at cjmurray@baltimorecountymd.gov or call 410-887-3480

Back to top

Pasturing and Stabling of Livestock – Public Input Meeting

A community input meeting is being held on Thursday, March 20, at 6 p.m. in Room 104, Jefferson Building, 105 W. Chesapeake Avenue in Towson, to gain input on the non-commercial raising and keeping of livestock, fowl or poultry on residential lots less than one acre, Council Resolution 73-13.

Please bring a written copy of your testimony to the hearing. Two minutes will be given to each speaker.

Information: Contact Jessie Bialek at jbialek@baltimorecountymd.gov or 410-887-3480

Back to top

Sewer Improvements

The Wilson Point Pumping Station will be improved and enlarged. Work officially began on December 18 and is expected to take a year to complete. Construction will cost $2,074,900.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Twin Rivers Pumping Station

The Twin Rivers Sewage Pumping Station at 13054 Harewood Road in Middle River will be extensively renovated in the next year. The project began in December last year and should be finished by January 14, 2015. The cost is $2,647,000.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Cowenton Avenue Sewers

Twenty-seven properties on Cowenton Avenue – from Panorama Drive north to 500 feet south of Joppa Road – will have access to the public sewage system within the coming year. Construction on this health job, costing $914,055, should take about seven months to complete.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Wye Road Pumping Station

The Wye Road Sewer Pumping Station, between Hopkins Creek and Norman Creek, in Middle River is being completely overhauled. Construction began in October last year and is expected to be finished by June. The cost is $979,000.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Hawthorne II Pumping Station

Public Works plans to begin renovating the Hawthorne II Sewage Pumping Station (on Cockspur Road, Middle River) this spring. The project will take a year to complete and cost $2,377,000.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Campbell Boulevard Phase 2

Campbell Boulevard, which will connect the existing Campbell Boulevard, off Bird River Road, to the existing Mohrs Lane, off Pulaski Highway, is under construction and should be completed in 2015. This three-lane road – with sidewalks – will be almost one mile long and cost $6 million.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Bengies Sewer Pumping Station

The Bengies Sewer Pumping Station is being extensively improved. Work, costing $6.47 million, began in late June last year and must be finished on November 24.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Mohrs Lane Bridge

The Mohrs Lane Bridge over the CSX Railroad, north of Pulaski Highway, was closed in 2007 because of structural deterioration. Demolition was completed by CSX in March 2011, at no cost to Baltimore County which has assumed ownership and plans to rebuild the span. A new bridge is currently being designed with construction scheduled for 2015. This bridge will be part of the future Campbell Boulevard Corridor.

Information: Email enginrng@baltimorecountymd.gov

Back to top

Administrative Variances

Administrative VariancesPending include requests for Administrative Variances pending before the Department of Permits, Approvals, and Inspections. These hearings are up to date as of publication of this newsletter and subject to change.
Information: Call the Office of Administrative Law Judges at 410-887-3868 or call Zoning Review at 410-887-3391

There were no Administrative Variances at the time of publication of the newsletter. Please visit the Administrative Variances calendar for any changes to District 6.

Back to top

Development Meetings

Development Meetings include Community Input, Concept Plan, County Review, Development Review Committee, and Hearing Officers Hearings. These hearings are up to date as of publication of this newsletter and subject to change.
Information: Call 410-887-3335

Development Review Committee Meeting - Stumpfs Road Property
Date/Time: Tuesday, March 18, 2 to 3 p.m.
Meeting Location: Room 123, County Office Building, 111 West Chesapeake Avenue, Towson, Maryland 21204
Project Location: 1210 Stumpfs Road
DRC Number: 031814-LLA1
Tracking Number: DRC-2014-00036
Request: The request is for a Lot Line Adjustment (LLA), to be forwarded to the Zoning Office for review and approval.
Information:
Colleen Kelly at CKelly@baltimorecountymd.gov or 410-887-3321

Development Review Committee Meeting - Franklin Square Medical Center MFSMC NICU
Date/Time: Tuesday, March 25, 2 to 3 p.m.
Meeting Location: Room 123, County Office Building, 111 West Chesapeake Avenue, Towson, Maryland 21204
Property Location: 9000 Franklin Square Drive
DRC Number: 032514D
PAI Number: 14-0315
Tracking Number: DRC-2014-00043
Request: The request is for a CRG refinement to construct a one-story building addition to the NICU.
Information:
Colleen Kelly at CKelly@baltimorecountymd.gov or 410-887-3321

Development Review Committee Meeting - Windlass Run Business Park
Date/Time: Tuesday, March 25, 2 to 3 p.m.
Meeting Location: Room 123, County Office Building, 111 West Chesapeake Avenue, Towson, Maryland 21204
Property Location: 11535 Crossroads Circle
DRC Number: 032514C
PAI Number: 15-0811
Tracking Number: DRC-2014-00042
Request: The request is for a development refinement for revisions on lots three and four.
Information: Colleen Kelly at CKelly@baltimorecountymd.gov or 410-887-3321

Back to top

Zoning Hearings

Zoning Hearings include Special Exceptions, Variances, and other issues before the Office of the Administrative Hearings of Baltimore County. These hearings are up to date as of publication of this newsletter and subject to change.

Information: Call the Office of Administrative Law Judges at 410-887-3868 or call Zoning Review at 410-887-3391

There are no Zoning Hearings scheduled at the time of publication of this newsletter. Please visit the Development and Zoning calendar for any changes to District 6.

Back to top